Week of October 23rd, 2023

Schodack

  • Muitzeskill Road: Restoration

  • Knickerbocker Road: Restoration

Milan

  • Limited Restoration

Clinton

  • Clinton Avenue: Restoration

Pleasant Valley

  • Limited Restoration.

Claverack

  • Baker Road: Laydown yard restoration

Week of October 9th, 2023

Milan

  • Limited Restoration.

Clinton

  • Maple Lane: Restoration.

Pleasant Valley

  • Krom Drive: Restoration

  • Smith Road: Restoration

Week of September 18, 2023

Milan

  • Pond Road: Restoration.

Clinton

  • Clinton Avenue: Restoration

Pleasant Valley

  • Limited Restoration

Week of September 11, 2023

Milan

  • Route 199: Restoration.

  • Pond Road: Restoration.

Clinton

  • Clinton Avenue: Restoration.

Pleasant Valley

  • Limited Restoration.

Week of September 4, 2023

Milan

  • Pond Road: Restoration.

Clinton

  • West Halstead Road: Restoration.

  • Clinton Avenue: Restoration

Pleasant Valley

  • Limited Restoration

Week of August 28, 2023

Milan

  • Route 199: Restoration.

  • Salisbury Turnpike: Restoration.

Clinton

  • Clinton Avenue: Restoration.

  • W Halstead Road: Restoration

Pleasant Valley

  • Limited Restoration.

Week of August 21, 2023

Milan

  • Route 199: Restoration.

  • Round Lake Road: Restoration.

  • Salisbury Turnpike: Restoration.

Clinton

  • West Halstead Road: Restoration.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Restoration.

  • Pleasant Valley Substation (Niagara Road): Restoration.

Week of August 14, 2023

Milan

  • Round Lake Road: Restoration.

  • Salisbury Turnpike: Restoration.

Clinton

  • West Halstead Road: Restoration.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Restoration.

  • Pleasant Valley Substation (Niagara Road): Restoration.

  • Kovacs Lane: Restoration.

Week of August 7, 2023

Claverack

  • Baker Road: Fence removal.

Milan

  • Pond Road: Restoration.

  • Round Lake Road: Restoration.

  • Salisbury Turnpike: Restoration.

Clinton

  • West Halstead Road: Restoration.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Restoration.

  • Pleasant Valley Substation (Niagara Road): Restoration.

  • Kovacs Lane: Restoration.

Week of July 31, 2023

Milan

  • Pond Road: Restoration.

  • Round Lake Road: Restoration.

Clinton

  • Clinton Avenue: Restoration.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Restoration.

  • Salt Point Turnpike: Restoration.

  • Kovacs Lane: Restoration.

Week of July 24, 2023

Clinton

  • Pond Road: Restoration.

  • Hollow Road: Restoration.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Restoration.

  • Salt Point Turnpike: Restoration.

  • Kovacs Lane: Restoration.

Week of July 17, 2023

Clinton

  • Turkey Hill Road: Restoration.

  • Pond Road: Restoration.

  • Salisbury Turnpike: Restoration.

  • Hollow Road: Restoration.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Restoration.

  • Ward Road: Restoration.

  • West Road: Restoration.

  • Ring Road: Restoration.

  • Salt Point Turnpike: Restoration.

  • Kovacs Lane: Restoration.

Week of July 10, 2023

Clinton

  • Turkey Hill Road: Restoration.

  • Pond Road: Restoration.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Restoration.

  • Ward Road: Restoration.

  • West Road: Restoration.

  • Ring Road: Restoration.

  • Salt Point Turnpike: Restoration.

  • Kovacs Lane: Restoration.

Week of June 26, 2023

Clinton

  • Ward Road: Restoration.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Restoration.

  • West Road: Restoration.

  • Ring Road: Restoration.

  • Kovacs Lane: Restoration.

Week of June 19, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Testing and commissioning, Reclamation and Restoration.

Clinton

  • Breezy Hill Road: Restoration.

  • Hollow Road: Restoration.

  • Ward Road: Restoration.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Restoration.

  • West Road: Restoration.

  • Kovacs Lane: Restoration.

Week of June 12, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Testing and commissioning, Reclamation and Restoration.

Clinton

  • Breezy Hill Road: Restoration.

  • Hollow Road: Restoration.

  • Ward Road: Restoration.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Restoration.

  • West Road: Restoration.

  • Kovacs Lane: Restoration.

Week of June 5, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Testing and commissioning, Reclamation and Restoration.

Claverack

  • Orchard Road: Restoration.

Livingston

  • White Oak Road: Restoration.

Clinton

  • Breezy Hill Road: Restoration.

  • Centre Road: Restoration.

  • Hollow Road: Restoration.

  • Schultzville Road: Restoration.

  • Ward Road: Restoration.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Restoration.

  • West Road: Restoration.

  • Kovacs Lane: Restoration.

Week of May 29, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Testing and commissioning, Reclamation and Restoration.

Claverack

  • Orchard Road: Restoration.

Livingston

  • White Oak Road: Restoration.

Milan

  • Turkey Hill Road: Restoration.

Clinton

  • Breezy Hill Road: Restoration.

  • Centre Road: Restoration.

  • Hollow Road: Restoration.

  • Nine Partners Road: Restoration.

  • Schultzville Road: Restoration.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Line work.

Week of May 22, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Testing and commissioning, Reclamation and Restoration.

Claverack

  • Orchard Road: Restoration.

Livingston

  • White Oak Road: Restoration.

Milan

  • Turkey Hill Road: Restoration.

Clinton

  • Breezy Hill Road: Restoration.

  • Centre Road: Restoration.

  • Hollow Road: Restoration.

  • Nine Partners Road: Restoration.

  • Schultzville Road: Restoration.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Line work.

Week of May 15, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Testing and commissioning, Reclamation and Restoration.

Claverack

  • Orchard Road: Restoration.

Livingston

  • White Oak Road: Restoration.

Milan

  • Turkey Hill Road: Restoration.

Clinton

  • Breezy Hill Road: Restoration.

  • Maple Lane: Restoration.

  • Nine Partners Road: Restoration.

  • Schultzville Road: Restoration.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Line and Lattice tower work.

  • Ward Road: Lattice tower leg removal.

  • Ring Road: Lattice tower leg removal.

  • Netherwood Road: Lattice tower leg removal.

  • Smith Road: Lattice tower leg removal.

Week of May 8, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Testing and commissioning, Reclamation and Restoration.

Milan

  • Battenfeld Road: Restoration.

  • Becker Hill Road: Restoration and AC Mitigation Restoration.

  • Spring Lake Road: AC Mitigation Restoration.

  • Turkey Hill Road: AC Mitigation Restoration.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of May 1, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Testing and commissioning, Reclamation and Restoration.

Milan

  • Battenfeld Road: Restoration.

  • Becker Hill Road: Restoration.

  • County Route 199: Restoration.

  • Milan Hill Road: Restoration.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of April 17, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Testing and commissioning, Access Road Realignment, and Restoration.

Livingston

  • Turkey Hill Road: Restoration.

Milan

  • Becker Hill Road: Restoration.

Clinton

  • Battenfeld Road: Restoration.

  • Centre Road: Wire work.

  • Nine Partners Road: Wire work.

  • Schultzville Road: Wire work.

  • West Halstead Road: Wire work and Fence repair.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Wire work and Line pull.

  • Pleasant Valley Substation (Niagara Road): Wire work and line pull.

  • Kovacs Lane: Restoration.

  • Netherwood Road: Wire work and restoration.

  • Salt Point Turnpike: Wire work and restoration.

Week of April 10, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Testing and commissioning.

Livingston

  • Turkey Hill Road: Restoration.

Milan

  • Becker Hill Road: Restoration.

Clinton

  • Battenfeld Road: Restoration.

  • Becker Hill Road: Restoration.

  • Centre Road: Wire work.

  • Nine Partners Road: Wire work.

  • Schultzville Road: Wire work.

  • West Halstead Road: Wire work and Fence repair.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Wire work and Line pull.

  • Pleasant Valley Substation (Niagara Road): Wire work and line pull.

  • Kovacs Lane: Restoration.

  • Netherwood Road: Wire work and restoration.

  • Salt Point Turnpike: Wire work and restoration.

Week of April 3, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Testing and commissioning.

Livingston

  • Snyderville Road: Restoration.

  • White Oak Road: Restoration.

Clinton

  • Breezy Hill Road: Timber removal and Wire testing.

  • Browning Road: Wire testing.

  • Centre Road: Wire work.

  • Clinton Avenue: Timber removal and Wire testing.

  • Clinton Hollow Road: Timber removal.

  • Hollow Road: Wire testing and Timber removal.

  • Nine Partners Road: Wire testing.

  • Schultzville Road: Wire testing.

  • West Halstead Road: Wire testing and Timber removal.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work and Matting and access installation.

  • Pleasant Valley Substation (Niagara Road): Civil work, Wire work, and Structure spotting.

  • Netherwood Road: Wire testing and Timber removal.

  • Ring Road: Wire work and testing.

  • Salt Point Turnpike: Timber removal and wire work and testing.

  • Ward Road: Wire work and testing.

Week of March 27, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Testing and commissioning.

Livingston

  • Church Road: Restoration.

  • County Route 8: Restoration.

  • Schneider Road: Restoration.

  • White Oak Road: Restoration.

Clinton

  • Breezy Hill Road: Timber removal.

  • Hollow Road: Wire pull and Timber removal.

  • Ring Road: Wire pull.

  • Schultzville Road: Wire pull.

  • Ward Road: Wire pull.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work and Matting and access installation.

  • Pleasant Valley Substation (Niagara Road): Civil work, Wire work, and Structure spotting.

  • Netherwood Road: Wire pull and Timber removal.

  • Salt Point Turnpike: Timber removal.

  • West Road: Timber removal.

  • Wigsten Road: Wire pull.

Week of March 20, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Testing and commissioning.

Livingston

  • County Route 8: Matting and access removal.

  • Jackson Corners Road: Matting and access removal.

  • Snyderville Road: Matting and access removal.

  • White Oak Road: Matting and access removal.

Milan

  • Deer Hill Road: Matting and access removal.

  • Milan Hill Road: Matting and access removal.

  • Pond Road: Matting and access removal.

  • Serenity Hill Road: Matting and access removal.

Clinton

  • Breezy Hill Road: Timber removal.

  • Browning Road: Wire pull.

  • Clinton Avenue: Wire pull.

  • County Route 18: Wire pull.

  • Hollow Road: Wire pull and Timber removal.

  • Ring Road: Wire pull.

  • Ward Road: Wire pull.

  • West Halstead Road: Wire pull.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work and Matting and access installation.

  • Pleasant Valley Substation (Niagara Road): Civil work, Wire work, and Structure spotting.

  • Netherwood Road: Wire pull and Timber removal.

  • Salt Point Turnpike: Wire work and Timber removal.

  • West Road: Wire work.

  • Wigsten Road: Wire work.

Week of March 13, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Wire pull and Testing.

Livingston

  • Church Road: Matting and access removal.

  • County Route 8: Matting and access removal.

  • Jackson Corners Road: Matting and access removal.

  • Schneider Road: Matting and access removal.

  • Snyderville Road: Matting and access removal.

  • White Oak Road: Matting and access removal.

Milan

  • County Route 199: Wire testing.

  • Deer Hill Road: Wire testing.

  • Milan Hill Road: Wire work and testing.

  • Milan Hollow Road: Wire testing.

  • Pond Road: Matting and access removal.

  • Round Lake Road: Wire testing.

  • Turkey Hill Road: Matting and access removal.

Clinton

  • Breezy Hill Road: Wire work and testing

  • Browning Road: Wire pull.

  • Clinton Avenue: Wire pull.

  • Clinton Hollow Road: Wire pull.

  • Maple Lane: Wire work.

  • Nine Partners Road: Wire work and testing.

  • Schultzville Road: Wire work.

  • Ward Road: Wire work.

  • West Halstead Road: Wire work.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work and Matting and access installation.

  • Pleasant Valley Substation (Niagara Road): Civil work, Wire work, and Structure spotting.

  • Netherwood Road: Wire work.

  • Salt Point Turnpike: Wire work.

  • West Road: Wire work.

  • Wigsten Road: Wire work.

Week of March 6, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Wire pull and Testing.

Livingston

  • Church Road: Matting and access removal.

  • County Route 8: Matting and access removal.

  • Deer Haven Road: Matting and access removal.

  • Jackson Corners Road: Matting and access removal.

  • Schneider Road: Matting and access removal.

  • Snyderville Road: Matting and access removal.

Milan

  • County Route 199: Wire testing.

  • Deer Hill Road: Wire testing.

  • Milan Hill Road: Wire work and testing.

  • Milan Hollow Road: Wire testing.

  • Pond Road: Wire testing.

  • Round Lake Road: Wire testing.

  • Salisbury Turnpike: Wire testing.

  • Serenity Hill Road: Wire testing.

Clinton

  • Breezy Hill Road: Wire work and testing

  • Browning Road: Wire work.

  • Bulls Head Road: Wire work.

  • Clinton Avenue: Wire work.

  • Maple Lane: Wire work and testing.

  • Nine Partners Road: Wire work and testing.

  • Schultzville Road: Wire work and testing.

  • West Halstead Road: Wire work.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work and Matting and access installation.

  • Pleasant Valley Substation (Niagara Road): Civil work, Wire work, and Structure spotting.

  • West Road: Wire transfer and lattice wreck-out.

  • Wigsten Road: Wire work.

Week of February 27, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Structure erection, Wire pull and Testing.

Claverack

  • County Route 2: Line testing.

  • County Route 20: Line testing.

  • County Route 22: Line testing.

  • County Route 66: Line testing.

  • Fish and Game Road: Line testing.

  • Orchard Road: Line testing.

  • Schoolhouse Road: Line testing.

  • Stone Mill Road: Line testing.

  • Webb Road: Line testing.

Livingston

  • Bells Pond Road: Line testing.

  • Black Bridge Road: Line testing and matting and access removal.

  • Church Road: Line testing.

  • County Route 8: Line testing.

  • County Route 82: Line testing and Matting and access removal.

  • Deer Haven Road: Line testing.

  • Jackson Corners Road: Line testing and matting and access removal.

  • Lockwood Road: Line testing.

  • Scudderhook Road: Line testing.

  • Snyderville Road: Line testing.

  • Turkey Hill Road: Line testing.

  • White Oak Road: Line testing.

Milan

  • Milan Hollow Road: Wire work.

  • Pond Road: Wire work.

Clinton

  • Breezy Hill Road: Wire work.

  • Browning Road: Wire work.

  • Bulls Head Road: Wire work.

  • Centre Road: Wire work.

  • Deer Hill Road: Wire work.

  • Maple Lane: Wire work.

  • Nine Partners Road: Wire work.

  • Schultzville Road: Wire work.

  • Serenity Hill Road: Wire work.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work and Matting and access installation.

  • Pleasant Valley Substation (Niagara Road): Civil work, Wire work, and Structure spotting.

  • Ward Road: Wire work and structure work.

Week of February 20, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Structure erection, and Wire pull.

Livingston

  • Bells Pond Road: Matting and access removal.

  • County Route 82: Matting and access removal.

  • County Route 19: Matting and access removal.

Milan

  • County Route 199: Wire work.

  • Milan Hill Road: Wire work.

  • Milan Hollow Road: Wire work.

  • Pond Road: Wire work.

  • Round Lake Road: Wire work.

  • Salisbury Turnpike: Wire work.

Clinton

  • Breezy Hill Road: Wire work.

  • Browning Road:Wire work.

  • Bulls Head Road: Wire work.

  • Centre Road: Wire work.

  • Deer Hill Road: Wire work.

  • Maple Lane: Wire work.

  • Nine Partners Road: Wire work.

  • Schultzville Road: Wire work.

  • Serenity Hill Road: Wire work.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work and Matting and access installation.

  • Pleasant Valley Substation (Niagara Road): Civil work, Wire work, and Structure spotting.

  • Wigsten Road: Wire work and structure work.

Week of February 13, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Structure spotting, and Electrical work.

Livingston

  • Bells Pond Road: Matting and access removal.

  • Black Bridge Road: Matting and access removal.

Milan

  • Battenfeld Road: Matting and access removal.

  • Becker Hill Road: Matting and access removal.

  • County Route 199: Wire work.

  • Milan Hill Road: Wire work.

  • Milan Hollow Road: Wire work.

  • Round Lake Road: Wire work.

  • Salisbury Turnpike: Wire work.

  • Turkey Hill Road: Matting and access removal.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work, Wire work, and Structure spotting.

  • West Road: Wire transfer and lattice wreck-out.

  • Wigsten Road: Wire transfer and lattice wreck-out.

Week of February 6, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Structure spotting, and Electrical work.

Claverack

  • Muitzeskill Road: Structure spotting.

  • Orchard Road: Matting and access removal.

Livingston

  • Estok Road: Matting and access removal.

Milan

  • County Route 199: Wire work.

  • Milan Hill Road: Wire work.

  • Milan Hollow Road: Wire work.

  • Pond Road: Wire work.

  • Round Lake Road: Wire work.

  • Salisbury Turnpike: Wire work.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work, Wire work, and Structure spotting.

  • Netherwood Road: Wire work.

  • Ring Road: Wire work.

  • Salt Point Turnpike: Structure spotting.

  • Smith Road: Wire work.

  • West Road: Wire work and Structure spotting.

  • Wigsten Road: Structure spotting.

Week of January 30, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Structural assembly, and Electrical work.

Claverack

  • Muitzeskill Road: Structure spotting.

Milan

  • Milan Hollow Road: Wire work.

  • Round Lake Road: Wire work.

  • Pond Road: Wire work.

Clinton

  • Clinton Avenue: Wire work.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work, Foundation drilling and pouring, Matting and access installation.

  • Netherwood Road: Wire work.

  • Ring Road: Wire work.

  • Salt Point Turnpike: Structure spotting.

  • West Road: Wire work and Structure spotting.

  • Wigsten Road: Structure spotting.

Week of January 23, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Structural assembly, and Electrical work.

Claverack

  • Route 9H: Matting and access removal.

  • Orchard Road: Matting and access removal.

  • NY-23B: Matting and access removal.

Milan

  • County Route 199: Structure work.

Clinton

  • Clinton Avenue: Structure work.

  • Ward Road: Structure work.

  • Deer Hill Road: Wire work.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work, Foundation drilling and pouring, Matting and access installation.

  • Salt Point Turnpike: Tree trimming.

  • Netherwood Road: Tree trimming.

  • Wigsten Road: Matting and access installation.

  • West Road: Structure work and Foundation drilling and pouring.

  • Smith Road: Foundation drilling.

Week of January 16, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Structural assembly, and Electrical work.

Claverack

  • Route 9H: Matting and access removal.

  • Orchard Road: Matting and access removal.

  • NY-23B: Matting and access removal.

Milan

  • County Route 199: Structure work.

Clinton

  • Clinton Avenue: Structure work.

  • Ward Road: Structure work.

  • Deer Hill Road: Wire work.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work, Foundation drilling and pouring, Matting and access installation.

  • Salt Point Turnpike: Tree trimming.

  • Netherwood Road: Tree trimming.

  • Wigsten Road: Matting and access installation.

  • West Road: Structure work and Foundation drilling and pouring.

  • Smith Road: Foundation drilling.

Week of January 9, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Structural assembly, and Electrical work.

Milan

  • County Route 199: Structure work.

Clinton

  • Clinton Avenue: Structure work.

  • Ward Road: Structure work.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work and Foundation drilling and pouring.

  • Salisbury Turnpike: Wire work and structure spotting.

  • Netherwood Road: Structure spotting and Structure assembly.

  • Deer Hill Road: Wire work.

  • Round Lake Road: Wire work and structure spotting.

  • Pond Road: Wire work.

  • West Road: Foundation drilling.

  • Smith Road: Foundation drilling and pouring

Week of January 3, 2023

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Structural assembly, and Electrical work.

Livingston

  • Black Bridge Road: Wire work.

  • Turkey Hill Road: Wire work.

Clinton

  • Centre Road: Structure work.

  • Hollow Road: Structure work.

  • Clinton Hollow Road: Structure work.

  • West Halstead Road: Structure work.

  • Browning Road: Structure work.

  • Clinton Avenue: Structure work.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Wire work and foundation drilling and pouring.

  • West Road: Foundation drilling and pouring and structure spotting.

  • Netherwood Road: Structure spotting.

  • Smith Road: Foundation drilling and pouring.

  • Salt Point Turnpike: Structure spotting.

  • Wigsten Road: Structure spotting.

  • Ring Road: Structure spotting.

Week of December 26, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Christmas break.

Milan

  • County Route 199: Structure work.

Clinton

  • Schultzville Road: Structure work.

  • Bulls Head Road: Structure work.

  • Nine Partners Road: Structure work.

  • Breezy Hill Road: Structure work.

  • Hollow Road: Structure work.

  • Maple Lane: Structure work.

  • Nine Partners Road: Structure work.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Christmas break.

  • Pleasant Valley Substation (Niagara Road): Christmas break.

  • Salt Point Turnpike: Structure work.

  • Netherwood Road: Structure work.

  • Smith Road: Structure work.

  • Round Lake Road: Structure work.

Week of December 19, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Structural assembly, and Electrical work.

Livingston

  • County Route 8: Wire work.

  • Jackson Corners Road: Wire work.

Milan

  • Turkey Hill Road: Wire work.

  • County Route 199: Wire work and structure spotting.

Clinton

  • Schultzville Road: Structure work.

  • Maple Lane: Structure work.

  • Nine Partners Road: Structure work.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Wire work and foundation drilling and pouring.

  • Kovacs Lane: Foundation drilling and pouring.

  • Netherwood Road: Foundation drilling and pouring.

  • Smith Road: Foundation drilling.

Week of December 12, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Structural assembly, and Electrical work.

Livingston

  • Black Bridge Road: Wire work.

  • County Route 8: Wire work.

  • Snyderville Road: Wire work.

  • White Oak Road: Wire work.

  • Weaver Road: Wire work.

  • Jackson Corners Road: Wire work.

  • Scudderhook Road: Matting and access installation.

Milan

  • Bulls Head Road: Structure spotting, New tower construction, Tree clearing, Foundation drilling and pouring.

  • Milan Hill Road: Wire work and New tower construction.

  • Becker Hill Road: Wire work.

  • Turkey Hill Road: Helicopter wire work

  • Battenfeld Road: Wire work.

  • Bulls Head Road: Structure spotting, New tower construction, tree clearing, and foundation drilling and pouring.

  • Round Lake Road: Structure spotting and tree clearing.

Clinton

  • Deer Hill Road: Structural spotting and tree clearing.

  • Pond Road: Structure spotting, New tower construction, Tree clearing, and Concrete pouring.

  • Breezy Hill Road: Tree and brush clearing.

  • Hollow Road: Tree and brush clearing.

  • Centre Road: Tree and brush clearing.

  • Serenity Hill Road: New tower construction, Tree clearing, and concrete pouring.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work; Traffic delays possible, please follow signage and flagmen.

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Salisbury Turnpike: Structure spotting.

Week of December 5, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Structural assembly, and Electrical work.

Livingston

  • Black Bridge Road: Wire work.

  • County Route 8: Wire work.

  • Lockwood Road: Matting and access installation.

  • White Oak Road: Wire work.

  • Weaver Road: Wire work.

  • Scudderhook Road: Matting and access installation.

Milan

  • Bulls Head Road: Structure spotting.

  • Milan Hollow Road: Wire work.

Clinton

  • Deer Hill Road: Structural work.

  • Pond Road: Foundation drilling.

  • Breezy Hill Road: Tree and brush clearing.

  • Hollow Road: Tree and brush clearing.

  • Clinton Hollow Road: Tree and brush clearing.

  • Schultzville Road: Tree and brush clearing.

  • Serenity Hill Road: Foundation drilling and pouring.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work; Traffic delays possible, please follow signage and flagmen.

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Niagara Road: Foundation drilling and pouring.

Week of November 28, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Structural assembly, and Electrical work.

Livingston

  • Black Bridge Road: Wire work.

  • Church Road: Matting and access installation

  • Lockwood Road: Matting and access installation.

  • White Oak Road: Wire work.

  • Weaver Road: Wire work.

  • Snyderville Road: Wire work.

  • Jackson Corners Road: Brush clearing

Milan

  • Turkey Hill Road: Wire work.

  • Becker Hill Road: Wire work.

  • Battenfeld Road: Wire work.

  • Milan Hill Road: Wire work.

Clinton

  • Deer Hill Road: Structural work.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work; Traffic delays possible, please follow signage and flagmen.

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Salisbury Turnpike: Structural work.

  • Wigsten Road: Matting and access installation.

  • Niagara Road: Foundation drilling.

Week of November 20, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Structural assembly, and Electrical work.

Livingston

  • Lockwood Road: Matting and access installation

  • Church Road: Matting and access installation

Milan

  • Turkey Hill Road: Wire work.

  • Becker Hill Road: Wire work.

  • Round Lake Road: Structural work.

  • Pond Road: Structural work.

  • Deer Hill Road: Structural work.

Clinton

  • Serenity Hill Road: Structural work.

  • Deer Hill Road: Structural work.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Salisbury Turnpike: Structural work.

Week of November 14, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Structural assembly, and Electrical work.

Livingston

  • Jackson Corners Road: Wire work.

  • Snyderville Road: Wire work

  • Estok Road: Restoration and reclamation

  • County Rd. 82: Restoration and reclamation.

  • Schneider Road: Restoration and reclamation.

Milan

  • Turkey Hill Road: Wire work.

  • Becker Hill Road: Wire work.

Clinton

  • Serenity Hill Road: Foundation drilling and pouring.

  • Browning Road: Foundation drilling and pouring.

  • Bulls Head Road: Foundation drilling and pouring.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • West Road: Matting and access installation.

  • Ring Road: Concrete pouring.

  • Niagara Road: Matting and access installation and Foundation drilling and pouring.

Week of November 7, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Structural assembly, and Electrical work.

Livingston

  • Jackson Corners Road: Wire work.

  • Snyderville Road: Wire work

  • Estok Road: Restoration and reclamation

  • County Rd. 82: Restoration and reclamation.

  • Schneider Road: Restoration and reclamation.

Milan

  • Turkey Hill Road: Wire work.

  • Becker Hill Road: Wire work.

Clinton

  • Serenity Hill Road: Foundation drilling and pouring.

  • Browning Road: Foundation drilling and pouring.

  • Bulls Head Road: Foundation drilling and pouring.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • West Road: Matting and access installation.

  • Ring Road: Concrete pouring.

  • Niagara Road: Matting and access installation and Foundation drilling and pouring.

Week of October 31, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Platform assembly, and Electrical work.

Livingston

  • Jackson Corners Road: Wire removal.

  • Snyderville Road: Wire work

Milan

  • Turkey Hill Road: Wire work.

  • Milan Hill Road: Wire work.

  • Battenfeld Road: Wire Work and Foundation drilling and pouring.

  • Becker Hill Road: Wire work and Foundation drilling and pouring.

Clinton

  • Clinton Hollow Road: Foundation drilling and pouring.

  • Browning Road: Foundation drilling and pouring.

  • Bulls Head Road: Matting and access installation

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • West Road: Matting and access installation.

  • Ward Road: Foundation drilling and pouring

  • Wigsten Road: Matting and access installation

  • Ring Road: Foundation drilling and pouring.

  • Niagara Road: Matting and access installation

  • Salt Point Turnpike: Foundation drilling and pouring.

Week of October 24, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Platform assembly, and Electrical work.

Livingston

  • Snyderville Road: Old Tower Removal, New Tower Assembly, Wire work

  • Jackson Corners Road: Old Tower Removal, Wire removal.

Milan

  • Turkey Hill Road: Wire removal.

  • Battenfeld Road: Foundation drilling.

Clinton

  • Clinton Avenue: Drill crews mobilizing and pouring.

  • Clinton Hollow Road: Foundation drilling and pouring.

  • West Halstead Road: Foundation drilling and pouring.

  • Browning Road: Foundation drilling and pouring.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Deer Hill Road: Matting and access installation.

  • West Road: Matting and access installation.

  • Ward Road: Foundation drilling and pouring and reclamation.

  • Ring Road: Matting and access Installation.

  • Salt Point Turnpike: Foundation drilling and pouring.

Week of October 17, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work, Platform assembly, and Electrical work.

Livingston

  • Snyderville Road: Old Tower Removal, New Tower Assembly, Wire work

  • Jackson Corners Road: Old Tower Removal, Wire removal.

Milan

  • Turkey Hill Road: Wire removal.

  • Battenfeld Road: Foundation drilling.

Clinton

  • Clinton Avenue: Drill crews mobilizing and pouring.

  • Clinton Hollow Road: Foundation drilling and pouring.

  • West Halstead Road: Foundation drilling and pouring.

  • Browning Road: Foundation drilling and pouring.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Deer Hill Road: Matting and access installation.

  • West Road: Matting and access installation.

  • Ward Road: Foundation drilling and pouring and reclamation.

  • Ring Road: Matting and access Installation.

  • Salt Point Turnpike: Foundation drilling and pouring.

Week of October 10, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

Livingston

  • Black Bridge Road: New Tower Assembly.

  • County Route 8: New Tower Assembly.

  • White Oak Road: Old Tower Removal, New Tower Assembly.

  • Snyderville Road: Old Tower Removal, New Tower Assembly.

  • Jackson Corners Road: Old Tower Removal.

Milan

  • Pond Road: Matting and access installation.

Clinton

  • Clinton Avenue: Drill crews mobilizing and pouring.

  • West Halstead Road: Foundation drilling and pouring.

  • Browning Road: Foundation drilling.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Niagara Road: Matting and access installation.

  • Ward Road: Matting and access Installation.

  • Ring Road: Matting and access Installation.

  • Salt Point Turnpike: Matting and access Installation, Foundation drilling.

  • West Road: Matting and access installation.

Week of September 26, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

Livingston

  • Black Bridge Road: New Tower Assembly.

  • County Route 8: New Tower Assembly.

  • White Oak Road: Old Tower Removal, New Tower Assembly.

  • Snyderville Road: Old Tower Removal, New Tower Assembly.

  • Jackson Corners Road: Old Tower Removal.

Milan

  • Pond Road: Matting and access installation.

Clinton

  • Clinton Avenue: Drill crews mobilizing and pouring.

  • West Halstead Road: Foundation drilling and pouring.

  • Browning Road: Foundation drilling.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Niagara Road: Matting and access installation.

  • Ward Road: Matting and access Installation.

  • Ring Road: Matting and access Installation.

  • Salt Point Turnpike: Matting and access Installation, Foundation drilling.

  • West Road: Matting and access installation.

Week of September 26, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

Livingston

  • Jackson Corners Road: Structure assembly.

  • Snyderville Road: Structure assembly.

  • Black Bridge Road: Structure assembly and wire installation.

Milan

  • Milan Hill Road: Structure assembly and drill crews mobilizing.

  • Battenfield Road: Structure assembly.

  • NY-199: Structure assembly.

  • Becker Hill Road: Structure assembly.

  • Turkey Hill Road: Structure assembly.

Clinton

  • Hollow Road: Foundation drilling and pouring.

  • Clinton Avenue: Drill crews mobilizing.

  • Clinton Hollow Road: Foundation drilling and pouring.

  • Schultzville Road: Foundation drilling and pouring.

  • Centre Road: Foundation drilling and pouring.

  • Breezy Hill Road: Foundation drilling and pouring.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Ring Road: Matting and access installation.

  • Ward Road: Matting and access installation.

  • Smith Road: Matting and access installation.

  • Wilbur Road: Matting and access installation.

  • Netherwood Road: Matting and access installation.

Week of September 19, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work

Livingston

  • Jackson Corners Road: Structure assembly

  • Snyderville Road: Structure assembly

  • Black Bridge Road: Wire installation

Milan

  • Milan Hill Road: Mobilization and foundation drilling

  • Milan Hollow Road: Matting and access installation

  • Deer Hill Road: Matting and access installation

  • Becker Hill Road: Structure assembly

  • Turkey Hill Road: Structure assembly

Clinton

  • Maple Lane: Foundation drilling and pouring.

  • Schultzville Road: Foundation drilling and pouring.

  • Centre Road: Foundation drilling and pouring.

  • Nine Partners Road: Foundation drilling and pouring.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Ring Road: Matting and access installation.

  • Salt Point Turnpike: Matting and access installation.

  • Netherwood Road: Matting and access installation.

Week of September 12, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring; excavations

Claverack

  • Churchtown Substation (Orchard Road): Structure delivery and assembly; wire transfer; old structure removal

Livingston

  • Maple Lane: Mobilization and foundation drilling

  • Deer Haven Road: Wire pull

  • Black Bridge Road: Wire pull

  • Lockwood Road: Structure assembly and wire pull

  • Schudderhook Road: Structure assembly and wire pull

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work

  • Pleasant Valley Substation (Niagara Road): Civil work

  • Ring Road: Mobilization and access installation

  • Ward Road: Mobilization and access installation

Week of September 5, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring; excavations

Claverack

  • Churchtown Substation (Orchard Road): Structure delivery and assembly; wire transfer; old structure removal

Livingston

  • Deer Haven Road: Wire pull

  • Black Bridge Road: Wire pull

  • Lockwood Road: Structure assembly and wire pull

  • Schudderhook Road: Structure assembly and wire pull

Clermont

  • County Route 8: Structure assembly and civil work

  • Country Route 19: Structure assembly and civil work

  • County Route 2: Structure assembly and civil work

  • Turkey Hill Road: Structure assembly and civil work

  • Milan Hill Road: Structure assembly and civil work

Milan

  • Milan Hill Road: Civil Work

Clinton

  • Centre Road: Foundation drilling and pouring

  • Nine Partners Road: Foundation drilling

  • Ward Road: Matting and access installation

  • Smith Road: Matting and access installation

  • Netherwood Road: Matting and access installation

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work

  • Pleasant Valley Substation (Niagara Road): Civil work

Week of August 29, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring; excavations

Claverack

  • Churchtown Substation (Orchard Road): Structure delivery and assembly; wire transfer; old structure removal

Livingston

  • Maple Lane: Mobilization and foundation drilling

  • Estok Road: Wire pull

  • Schneider Road: Stucture assembly and wire pull

  • Church Road: Structure assembly and wire pull

  • Lockwood Road: Structure assembly and wire pull

  • Schudderhook Road: Structure assembly and wire pull

Milan

  • Milan Hill Road: Concrete pouring

Clinton

  • Centre Road: Foundation drilling and pouring

  • Schultzville Road: Foundation drilling

  • Bulls Head Road: Foundation drilling

  • Clinton Hollow Road: Foundation drilling and pouring

  • Hollow Road: Foundation drilling and pouring

  • Browning Road: - Access installation and foundation drilling

  • West Halstead Road: Matting and access installation

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work

  • Pleasant Valley Substation (Niagara Road): Civil work

Week of August 22, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring; excavations

Claverack

  • Churchtown Substation (Orchard Road): Structure delivery and assembly; wire transfer; old structure removal

Livingston

  • Maple Lane: Mobilization and foundation drilling

  • Estok Road: Wire pull

  • Schneider Road: Stucture assembly and wire pull

  • Church Road: Structure assembly and wire pull

  • Lockwood Road: Structure assembly and wire pull

  • Scudderhook Road: Structure assembly and wire pull

Milan

  • Round Lake Road: Foundation drilling and pouring

  • Pond Road: Foundation drilling and pouring

  • Route 199: Foundation drilling and pouring

  • Milan Hill Road: Foundation drilling and pouring

Clinton

  • Nine Partners Road: Matting and access installation

  • Clinton Avenue: Matting and access installation

  • Hollow Road: Matting and access installation

  • West Halstead Road: Matting and access installation

  • Clinton Hollow Road: Matting and access installation

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work

  • Pleasant Valley Substation (Niagara Road): Civil work

Week of August 15, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring; excavations.

Claverack

  • Churchtown Substation (Orchard Road): Structure delivery and assembly; wire transfer; old structure removal.

  • Stone Mill Road: Restoration and reclamation.

Livingston

  • Estok Road: Structure assembly and wire pull.

  • Lockwood Road: Structure assembly and wire pull.

  • Scudderhook Road: Structure assembly and wire pull.

  • Bells Pond Road: Structure Assembly and wire pull.

Milan

  • Milan Hollow Road: Foundation drilling and pouring.

  • Milan Hill Road: Foundation drilling and pouring.

Clinton

  • Nine Partners Road: Matting and access installation.

  • Breezy Hill Road: Matting and access installation.

  • West Halstead Road: Matting and access installation.

  • Clinton Ave: Mobilize crews.

  • Schultzville Road: Matting and access installation.

  • Hollow Road: Matting and access installation.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of August 8, 2022

Claverack

  • Churchtown Substation (Orchard Road): Structure delivery and assembly; wire pull.

  • Stone Mill Road: Restoration and reclamation.

  • Church Road: Structure delivery and assembly; wire transfer; old structure removal.

  • Route 9H: Mobilize equipment.

Clinton

  • Nine Partners Road: Matting and access installation.

  • Breezy Hill Road: Matting and access installation.

Livingston

  • NY-82: Structure delivery and assembly; wire pull.

  • Estok Road: Structure delivery and assembly; wire pull.

  • Route 8: Structure assembly and wire pull.

  • Church Road: Structure delivery and assembly; wire pull.

  • Lockwood Road: Structure delivery and assembly; wire pull.

  • Scudderhook Road: Structure delivery and assembly; wire pull.

  • Blue Stores Substation (U.S. Highway 9): Structure removal, civil and below-grade work.

Milan

  • Round Lake Road: Foundation drilling.

  • Milan Hill Road: Foundation drilling and pouring.

  • Milan Hollow Road: Foundation drilling.

  • Salisbury Turnpike: Foundation drilling and pouring.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of August 1, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring; excavations.

Claverack

  • Churchtown Substation (Orchard Road): Structure delivery and assembly; wire transfer; old structure removal.

  • Webb Road: Restoration and reclamation.

Clinton

  • Bulls Head Road: Matting and access installation.

  • Maple Lane: Matting and access installation.

  • Nine Partners Road: Matting and access installation.

  • Breezy Hill Rd: Matting and access installation.

  • Centre Rd: Matting and access installation.

Livingston

  • NY-82: Structure assembly and wire pull.

  • Estok Road: Structure assembly and wire pull.

  • Church Road: Structure assembly and wire pull.

  • Lockwood Road: Structure assembly and wire pull.

  • Scudderhook Road: Structure assembly and wire pull.

  • Blackbridge Road: Structure assembly and wire pull.

  • Blue Stores Substation (U.S. Highway 9): Structure removal, civil and below-grade work.

Milan

  • Becker Hill Road: Foundation drilling and pouring.

  • Salisbury Turnpike: Foundation drilling and pouring.

  • Turkey Hill Road: Foundation drilling and pouring.

  • Milan Hill Road: Foundation drilling and pouring.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of July 25, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring; excavations.

Claverack

  • Churchtown Substation (Orchard Road): Structure delivery and assembly; wire transfer; old structure removal.

  • Schneider Road: Structure delivery and assembly; wire transfer; old structure removal.

  • Church Road: Structure delivery and assembly; wire transfer; old structure removal.

  • Union Turnpike: Restoration and reclamation.

  • Fish and Game Road: Restoration and reclamation.

Clinton

  • Bulls Head Road: Matting and access installation.

  • Maple Lane: Matting and access installation.

  • Nine Partners Road: Matting and access installation.

  • Schultzville Road: Matting and access installation.

Livingston

  • NY-82: Structure delivery and assembly; wire pull.

  • Estok Road: Structure delivery and assembly; wire pull.

  • Schneider Road: Structure delivery and assembly; wire pull.

  • Church Road: Structure delivery and assembly; wire pull.

  • Lockwood Road: Structure delivery and assembly; wire pull.

  • Scudderhook Road: Structure delivery and assembly; wire pull.

  • Blackbridge Road: Structure delivery and assembly; wire pull.

  • Blue Stores Substation (U.S. Highway 9): Structure removal, civil and below-grade work.

Milan

  • Battenfeld Road: Foundation drilling and pouring.

  • Becker Hill Road: Foundation drilling and pouring.

  • County Route 8: Foundation drilling and pouring.

  • Salisbury Turnpike: Foundation drilling and pouring.

  • Turkey Hill Road: Foundation drilling and pouring.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of July 18, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring; excavations.

Claverack

  • Churchtown Substation (Orchard Road): Structure delivery and assembly; wire transfer; old structure removal.

Clinton

  • Bulls Head Road: Matting and access installation.

  • Maple Lane: Matting and access installation.

  • Nine Partners Road: Matting and access installation.

Livingston

  • Bells Pond Road: Structure delivery and assembly; wire transfer; old structure removal.

  • NY-82: Structure delivery and assembly; wire transfer; old structure removal.

  • Estok Road: Structure removal.

  • Schneider Road: Structure removal.

  • Church Road: Structure removal.

  • Lockwood Road: Structure removal.

  • Scudderhook Road: Structure removal.

  • Blackbridge Road: Structure removal.

  • White Oak Road: Reclamation; restoration.

  • County Route 19: Structure removal.

  • County Route 8: Foundation drilling and pouring; reclamation and restoration.

  • Blue Stores Substation (U.S. Highway 9): Structure removal, civil and below-grade work.

Milan

  • Round Lake Road: Matting and access installation.

  • Pond Road: Matting and access installation.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of July 11, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring; excavations.

Claverack

  • Stottville Road: Reclamation; restoration.

  • Churchtown Substation (Orchard Road): Structure delivery and assembly; wire transfer; old structure removal.

Ghent

  • NY-20: Reclamation; restoration.

Livingston

  • Bells Pond Road: Structure delivery and assembly; wire transfer; old structure removal.

  • NY-82: Structure delivery and assembly; wire transfer; old structure removal.

  • Estok Road: Structure removal.

  • Schneider Road: Structure removal.

  • Church Road: Structure removal; foundation drilling and pouring.

  • Lockwood Road: Structure removal.

  • Orchard Road: Foundation drilling and pouring.

  • Scudderhook Road: Structure removal.

  • Blackbridge Road: Structure removal.

  • White Oak Road: Structure removal.

  • County Route 19: Structure removal; foundation drilling and pouring.

  • County Route 8: Structure removal; foundation drilling and pouring.

  • Blue Stores Substation (U.S. Highway 9): Structure removal, civil and below-grade work.

Milan

  • NY-199: Matting and access installation.

  • Salisbury Turnpike: Matting and access installation.

  • Round Lake Road: Matting and access installation.

  • Pond Road: Matting and access installation.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of July 4, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring; excavations.

Claverack

  • Stottville Road: Reclamation; restoration.

  • Union Turnpike: Reclamation; restoration.

  • Churchtown Substation (Orchard Road): Structure delivery and assembly; wire transfer; old structure removal.

Livingston

  • Bells Pond Road: Structure delivery and assembly; wire transfer; old structure removal.

  • NY-82: Structure delivery and assembly; wire transfer; old structure removal.

  • Estok Road: Structure removal.

  • Schneider Road: Structure removal.

  • Church Road: Structure removal.

  • Lockwood Road: Structure removal.

  • Scudderhook Road: Structure removal.

  • Blackbridge Road: Structure removal.

  • White Oak Road: Structure removal.

  • County Route 19: Structure removal.

  • County Route 8: Structure removal.

  • Blue Stores Substation (U.S. Highway 9): Structure removal, civil and below-grade work.

Milan

  • NY-199: Matting and access installation.

  • Salisbury Turnpike: Matting and access installation.

  • Round Lake Road: Mobilization; Matting and access installation.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of June 27, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring; excavations.

Stockport

  • Begos Road: Reclamation; restoration.

Ghent

  • Begos Road: Reclamation; restoration.

  • County Route 20: Reclamation; restoration.

Claverack

  • Bells Pond Road: Structure delivery and assembly; wire transfer; old structure removal.

  • Webb Road: Worksite clean-up.

  • Stone Mill Road: Worksite clean-up.

  • Route 9H & 23: Worksite clean-up.

  • Churchtown Substation (Orchard Road): Structure delivery and assembly; wire transfer; old structure removal.

Livingston

  • Bells Pond Road: Structure delivery and assembly; wire transfer; old structure removal.

  • NY-82: Structure delivery and removal.

  • Estok Road: Structure delivery and removal.

  • Schneider Road: Structure delivery and removal.

  • Church Road: Structure delivery and removal.

  • Lockwood Road: Structure delivery and removal.

  • Scudderhook Road: Structure delivery and removal.

  • Blackbridge Road: Structure delivery and assembly; wire transfer; old structure removal.

  • White Oak Road: Structure delivery and removal.

  • County Route 19: Structure delivery and removal.

  • Blue Stores Substation (U.S. Highway 9): Civil and below-grade work.

Milan

  • Turkey Hill Road: Drill and pour foundations.

  • Salisbury Turnpike: Matting and access installation.

  • Round Lake Road: Mobilization; matting and access installation.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of June 20, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring; excavations.

Ghent

  • West Ghent Road: Reclamation; restoration.

  • Begos Road: Reclamation; restoration.

Claverack

  • NY-23B: Wire Installation.

  • Webb Road: Worksite clean-up.

  • Stone Mill Road: Worksite clean-up.

  • Route 9H & 23: Worksite clean-up.

  • Churchtown Substation (Orchard Road): Structure delivery and assembly; wire transfer; old structure removal.

Livingston

  • Bells Pond Road: Structure delivery.

  • NY-82: Structure delivery.

  • Estok Road: Structure delivery.

  • Schneider Road: Structure delivery.

  • Church Road: Structure delivery.

  • Lockwood Road: Structure delivery.

  • Scudderhook Road: Structure delivery.

  • Blackbridge Road: Structure delivery.

  • White Oak Road: Structure delivery.

  • County Route 19: Structure delivery.

  • Blue Stores Substation (U.S. Highway 9): Civil and below-grade work.

Gallatin

  • Snyderville Road: Drill and pour foundations.

Clermont

  • Turkey Hill Road: Drill and pour foundations.

Milan

  • Turkey Hill Road: Drill and pour foundations.

  • Becker Hill Road: Matting and access installation.

  • Battenfeld Road: Matting and access installation.

  • NY-199: Mobilization; Matting and access installation.

  • Salisbury Turnpike: Matting and access installation.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

Pleasant Valley Substation (Niagara Road): Civil work.

Week of June 6, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring.

Ghent

  • West Ghent Road: Mobilization; restoration.

Claverack

  • NY-23B: Wire pull.

  • Webb Road: Wire pull.

  • Stone Mill Road: Wire pull.

  • Route 9H & 23: Wire pull.

  • Churchtown Substation (Orchard Road): Wire pull; restoration.

Livingston

  • Blackbridge Road: Drill and pour foundations.

  • White Oak Road: Drill and pour foundations.

  • Blue Stores Substation (U.S. Highway 9): Civil and below-grade work.

Gallatin

  • Snyderville Road: Matting and access installation; drill and pour foundations.

Milan

  • Turkey Hill Road: Matting and access installation.

  • Beckerhill Road: Matting and access installation.

  • Battenfeld Road: Matting and access installation.

  • NY-199: Mobilization

  • Salisbury Turnpike: Mobilization

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work; structure assembly; wire work.

  • Pleasant Valley Substation (Niagara Road): Civil work.
    Week of May 30, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring.

Stockport

  • Knitt Road: Restoration.

Claverack

  • NY-23B: Wire pull preparations.

  • Webb Road: Structure removal, assembly, and installation.

  • Stone Mill Road: Structure removal, delivery, assembly and, installation.

  • Route 9H & 23: Wire work.

  • Churchtown Substation (Orchard Road): re-energization; set up for wire pull; restoration.

Livingston

  • Lockwood Road: Drill and pour foundations.

  • Blackbridge Road: Drill and pour foundations.

  • County Route 8: Drill and pour foundations.

  • White Oak Road: Drill and pour foundations.

  • County Route 19: Matting and access installation.

  • Blue Stores Substation (U.S. Highway 9): Civil and below-grade work.

Gallatin

  • Snyderville Road: Matting and access installation; drill and pour foundations.

Milan

  • Turkey Hill Road: Matting and access installation.

  • Beckerhill Road: Matting and access installation.

  • Battenfeld Road: Matting and access installation.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work; structure assembly; wire work.

  • Pleasant Valley Substation (Niagara Road): Civil work.


Week of May 23, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring; matting and access installation.

Ghent

  • West Ghent Road: Restoration.

Claverack

  • Route 66: Restoration.

  • Webb Road: Structure removal, delivery, assembly and, installation.

  • Stone Mill Road: Structure removal, delivery, assembly and, installation.

  • Route 9H & 23: Wire work.

  • Churchtown Substation (Orchard Road): re-energization.

Livingston

  • Estok Road: Structure delivery.

  • Lockwood Road: Drill and pour foundations; Structure delivery.

  • Scudderhook Road: Drill and pour foundations; Structure delivery.

  • Deer Haven Road: Drill and pour foundations; Structure delivery.

  • County Route 19: Matting and access installation.

  • White Oak Road: Matting and access installation.

  • Blue Stores Substation (U.S. Highway 9): Civil and below-grade work.

Gallatin

  • Snyderville Road: Matting and access installation.

  • Jackson Corners Road: Matting and access installation.

  • Turkey Hill Road: Matting and access installation.

Milan

  • Turkey Hill Road: Matting and access installation.

  • Beckerhill Road: Matting and access installation.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work; structure assembly; wire work.

  • Pleasant Valley Substation (Niagara Road): Civil work.


Week of May 16, 2022

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring.

Stuyvesant

  • Route 26A: Restoration.

  • U.S. Hwy 9: Restoration.

Stockport

  • Knitt Road: Restoration.

Claverack

  • Route 66: Restoration.

  • Webb Road: Structure assembly.

  • Stone Mill Road: Structure removal, delivery, and assembly.

  • Route 9H & 23: Wire work.

  • Churchtown Substation (Orchard Road): Testing and commissioning.

Livingston

  • NY-82: Drill and pour foundations; structure delivery.

  • Estok Road: Drill and pour foundations; structure delivery.

  • Church Road: Matting and access installation.

  • Deer Haven Road: Structure delivery; mobilization.

  • County Route 8: Matting and access installation.

  • White Oak Road: Matting and access installation.

  • Blue Stores Substation (U.S. Highway 9): Civil and below-grade work.

Gallatin

  • Snyderville Road: Matting and access installation.

  • Turkey Hill Road: Matting and access installation.

Milan

  • Turkey Hill Road: Matting and access installation.

Clinton

  • Maple Lane: Mowing and handcutting of vegetation; matting and access installation.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work; structure assembly; wire work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of May 9, 2022

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring.

Stuyvesant

  • Route 26A: Restoration.

  • U.S. Hwy 9: Restoration.

Stockport

  • Knitt Road: Restoration.

Claverack

  • Route 66: Restoration.

  • Webb Road: Structure assembly.

  • Stone Mill Road: Structure removal, delivery, and assembly.

  • Route 9H & 23: Wire work.

  • Churchtown Substation (Orchard Road): Testing and commissioning.

Livingston

  • NY-82: Drill and pour foundations; structure delivery.

  • Estok Road: Drill and pour foundations; structure delivery.

  • Church Road: Matting and access installation.

  • Deer Haven Road: Structure delivery; mobilization.

  • County Route 8: Matting and access installation.

  • White Oak Road: Matting and access installation.

  • Blue Stores Substation (U.S. Highway 9): Civil and below-grade work.

Gallatin

  • Snyderville Road: Matting and access installation.

  • Turkey Hill Road: Matting and access installation.

Milan

  • Turkey Hill Road: Matting and access installation.

Clinton

  • Maple Lane: Mowing and handcutting of vegetation; matting and access installation.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work; structure assembly; wire work.

  • Pleasant Valley Substation (Niagara Road): Civil work.


Week of May 2, 2022

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring.

Stockport

  • County Route 25: Restoration.

Ghent

  • Gilligan Road: Restoration.

Claverack

  • Route 66: Restoration.

  • Webb Road: Structure delivery.

  • Stone Mill Road: Structure removal, delivery, and assembly.

  • Route 9H & 23: Wire work.

  • Churchtown Substation (Orchard Road): Testing and commissioning.

Livingston

  • NY-82: Drill and pour foundations; structure delivery.

  • Estok Road: Drill and pour foundations; structure delivery.

  • Church Road: Matting and access installation.

  • Deer Haven Road: Structure delivery; mobilization.

  • County Route 8: Matting and access installation.

  • White Oak Road: Matting and access installation.

  • Blue Stores Substation (U.S. Highway 9): Civil and below-grade work.

Gallatin

  • Turkey Hill Road: Matting and access installation.

Clinton

  • Maple Lane: Mowing and handcutting of vegetation; matting and access installation.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work; structure assembly; wire work.

Pleasant Valley Substation (Niagara Road): Civil work.


Week of April 25, 2022

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring.

Stuyvesant 

  • County Road 26A: Restoration.

Stockport

  • County Route 25: Restoration.

Ghent

  • Gilligan Road: Restoration.

Claverack

  • Route 66: Restoration.

  • Route 23B: Wire work; structure removal and assembly.

  • Webb Road: Drill and pour foundations.

  • Stone Mill Road: Drill and pour foundations.

  • Churchtown Substation (Orchard Road): Above-grade structural work; structure delivery, removal, and assembly.

Livingston

  • Bells Pond Road: Drill and pour foundations.

  • NY-82: Drill and pour foundations; structure delivery.

  • Estok Road: Structure delivery.

  • Schneider Road: Structure delivery.

  • Church Road: Matting and access installation.

  • Lockwood Road: Matting and access installation.

  • Scudderhook Road: Structure delivery.

  • Deer Haven Road: Structure delivery.

  • County Route 19: Drill and pour foundations; matting and access installation.

  • County Route 8: Matting and access installation.

  • White Oak Road: Matting and access installation.

  • Blue Stores Substation (U.S. Highway 9): Civil and below-grade work.

Gallatin

  • Turkey Hill Road: Matting and access installation.

Clinton

  • Maple Lane: Mowing and handcutting of vegetation.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work; structure assembly; wire work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of April 18, 2022

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring.

Stuyvesant

  • C.R. 26A: Restoration.

Ghent

  • Gilligan Road: Restoration.

  • Begos Road: Restoration.

Claverack

  • Fish and Game Road: Wire work.

  • Webb Road: Structure removal.

  • Stone Mill Road: Temporary wood pole installation; structure removal; drill and pour foundations.

  • Churchtown Substation (Orchard Road): Above-grade structural work; structure delivery; drill and pour foundations.

Livingston

  • NY-82: Structure delivery.

  • Estok Road: Structure delivery.

  • Schneider Road: Structure delivery.

  • Church Road: Matting and access installation.

  • Lockwood Road: Matting and access installation.

  • Scudderhook Road: Structure delivery.

  • Deerhaven Road: Structure delivery; drill and pour foundations.

  • County Route 19: Matting and access installation.

  • Blue Stores Substation (U.S. Highway 9): Civil and below-grade work.

Clinton

  • Maple Lane: Site preparations.

  • Clinton Avenue: Site preparations.

Pleasant Valley

  • Ward Road: Flagging and staking.

  • Ring Road: Flagging and staking.

  • Netherwood Road: Flagging and staking.

  • Salt Point Turnpike: Flagging and staking.

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work; structure assembly; wire work.

  • Pleasant Valley Substation (Niagara Road): Civil work.


Week of April 11, 2022

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; foundation drilling and pouring.

Stuyvesant 

  • County Road 26A: Restoration.

Ghent

  • Begos Road: Restoration.

Claverack

  • Fish and Game Road: Wire work; structure assembly.

  • Webb Road: Temporary wood pole delivery; prep for structure removal.

  • Stone Mill Road: Temporary wood pole delivery; Drill and pour foundations.

  • Churchtown Substation (Orchard Road): Civil and below-grade work; construction of switching station; structure delivery.

Livingston

  • NY-82: Structure delivery.

  • Estok Road: Structure delivery.

  • Schneider Road: Structure delivery.

  • Scudderhook Road: Matting and access installation; structure delivery.

  • Deer Haven Road: Drill and pour foundations; Structure delivery.

  • County Route 8: Matting and access installation; drill and pour foundations.

  • Blue Stores Substation (U.S. Highway 9): Civil and below-grade work.

Gallatin

  • Turkey Hill Road: Matting and access installation.

Clinton

  • Clinton Hollow Road: Mowing and handcutting of vegetation.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.


Week of April 4, 2022

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

Stuyvesant 

  • County Road 26A: Restoration.

Stockport

  • Knitt Road : Restoration.

Claverack 

  • Route 66: Wire work.

  • Fish and Game Road: Wire work.

  • Stone Mill Road: Drill and pour foundations.

  • Churchtown Substation (Orchard Road): Construction of switching station.

Livingston

  • Schneider Road: Matting and access installation.

  • Scudderhook Road: Matting and access installation.

  • Deer Haven Road: Drill and pour foundations.

  • County Route 8: Matting and access installation.

  • Blue Stores Substation (U.S. Highway 9): Civil and below-grade work.

Clinton

  • Clinton Hollow Road: Mowing and handcutting of vegetation.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Civil work.

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of March 28, 2022

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; matting and access installation; foundation drilling and pouring.

Stuyvesant 

  • County Road 26A: Restoration.

Stockport

  • Hudson Avenue (CR-25): Restoration.

Claverack 

  • Route 66: Wire pull preparations; wire pull.

  • Fish and Game Road: Wire pull preparations; wire pull; structure removal and assembly.

  • NY-23B: Drill and pour foundations.

  • Churchtown Substation (Orchard Road): Civil and below-grade work; construction of switching station.

Livingston

  • NY-82: Matting and access installation.

  • Schneider Road: Matting and access installation.

  • Scudderhook Road: Matting and access installation.

  • Deer Haven Road: Drill and pour foundations.

  • County Route 8: Matting and access installation.

  • Blue Stores Substation (U.S. Highway 9): Civil and below-grade work.

Milan

  • Round Lake Road: Site preparations.

  • Pond Road: Site preparations.

  • Breezy Hill Road: Flagging and staking.

Clinton

  • Clinton Hollow Road: Mowing and handcutting of vegetation.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Structure removal; structure delivery and assembly.

  • Pleasant Valley Substation (Niagara Road): Civil work.
    Week of March 14, 2022

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; drill and pour foundations; wire work.

Stuyvesant 

  • County Road 26A: Restoration.

Stockport

  • U.S. Highway 9: Restoration.

  • Hudson Avenue (CR-25): Restoration.

Claverack 

  • Route 66: Drill and pour foundations; structure removal; structure delivery and assembly; wire work.

  • Fish and Game Road: Drill and pour foundations; structure removal; structure delivery and assembly; wire work.

  • NY-23B: Structure delivery and assembly; drill and pour foundations.

  • Churchtown Substation (Orchard Road): Civil and below-grade work; construction of switching station; structure delivery and assembly; wirework.

Livingston

  • NY-82: Matting and access installation.

  • Deer Haven Road: Matting and access installation.

  • County Route 19: Matting and access installation.

  • County Route 8: Matting and access installation.

  • Blue Stores Substation (U.S. Highway 9): Civil and below-grade work.

Milan

  • Milan Hill Road: Site Preparations.

  • Route 199: Site Preparations.

  • Salisbury Turnpike: Site Preparations.

  • Round Lake Road: Site Preparations.

  • Pond Road: Site Preparations.

  • Milan Hollow Road: Site Preparations.

  • Maple Lane: Flagging and staking.

  • Ward Road: Flagging and staking.

Pleasant Valley

  • Netherwood Road: Flagging and staking.

  • Smith Road: Flagging and staking.

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Structure removal; structure delivery and assembly.

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of March 7, 2022

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; drill and pour foundations; wire work.

Stuyvesant 

  • Ridge Road: Restoration.

  • County Road 26A: Restoration.

Stockport

  • U.S. Highway 9: Restoration.

Claverack 

  • Route 66: Drill and pour foundations; Structure removal; Structure delivery and assembly; wire work.

  • Fish and Game Road: Structure delivery and assembly; wire work; drill and pour foundations.

  • NY-23B: Structure delivery and assembly; drill and pour foundations.

  • NY-9H and 23: Structure delivery and assembly.

  • Churchtown Substation (Orchard Road): Civil and below-grade work; construction of switching station; Structure delivery and assembly.

Livingston

  • Schneider Road: Matting and access installation.

  • Church Road: Mowing and handcutting of vegetation.

  • Deer Haven Road: Matting and access installation.

  • County Route 19: Matting and access installation.

  • Blue Stores Substation (County Route 19): Civil work.

Milan

  • Salisbury Turnpike: Flagging and staking.

  • Round Lake Road: Flagging and staking.

Pleasant Valley

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Structure removal; structure delivery and assembly; flagging and staking.

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of February 28, 2022

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; drill and pour foundations; wire work.

Stuyvesant 

  • Schoolhouse Road: Restoration.

  • County Road 26A: Restoration.

Stockport

  • West Ghent Road: Wire work.

Ghent

  • Gilligan Road: Wire work.

  • Begos Road: Wire work.

  • County Road 20: Wire work.

Claverack 

  • Fish and Game Road: Structure delivery; wire work; drill and pour foundations.

  • Route 66: Structure assembly; wire work.

  • Churchtown Substation (Orchard Road): Civil and below-grade work; construction of switching station.

Livingston

  • Estok Road: Matting and access installation.

  • Lockwood Road: Matting and access installation.

  • Deer Haven Road: Matting and access installation.

  • County Route 19: Matting and access installation.

  • Blue Stores Substation (County Route 19): Civil work.

Pleasant Valley

  • Netherwood Road: Flagging and staking.

  • Van Wagner Sub: Flagging and staking.

  • Pleasant Valley Substation (Niagara Road): Civil work.

    Week of February 21, 2022

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; drill and pour foundations.

Stuyvesant 

  • Ridge Road: Restoration.

  • County Road 26A: Restoration.

  • County Road 46: Restoration.

Stockport

  • West Ghent Road: Wire work; Pulling wire.

Ghent

  • Gilligan Road: Wire work; Pulling wire.

  • Begos Road: Wire work; Pulling wire.

  • County Road 20: Wire work; Pulling wire.

Claverack 

  • Fish and Game Road: Drill and pour foundations.

  • Schoolhouse Road- Route 9H and 23B: Drill and pour foundations.

  • Orchard Road: Drill and pour foundations.

  • Churchtown Substation (Orchard Road): Civil and below-grade work; construction of switching station.

Livingston

  • Estok Road: Matting and access installation.

  • Schneider Road: Matting and access installation.

  • Deer Haven Road: Matting and access installation.

  • Blue Stores Substation (County Route 19): Civil work.

Clinton

  • W. Halstead Road: Flagging and staking.

  • Netherwood Road: Flagging and staking.

Pleasant Valley

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of February 7, 2022

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; drill and pour foundations.

Stuyvesant 

  • Schoolhouse Road: Restoration.

  • Hollow Road: Restoration.

Stockport

  • West Ghent Road: Drill and pour foundations.

Ghent

  • County Road 20: Pulling wire.

Claverack 

  • Stottville Road: Pulling wire.

  • Mountain View Road: Pulling wire.

  • Route 66: Pulling wire.

  • Stone Mill Road: Handcutting and mechanized removal of vegetation and trees.

  • Schoolhouse Road- Route 9H and 23B: Drill and pour foundations.

  • Churchtown Substation (Orchard Road): Civil and below-grade work; construction of switching station.

Livingston

  • Bells Pond Road: Mowing and handcutting of vegetation; matting and access installation.

  • Estok Road: Mowing and handcutting of vegetation; matting and access installation.

  • Church Road: Vegetation and tree removal.

  • Black Bridge-Deer Haven Road: Matting and access installation.

  • Blue Stores Substation (County Route 19): Civil work.

Clinton

  • Bulls Head Road: Flagging and staking.

  • Maple Lane: Flagging and staking.

Pleasant Valley

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Drill and pour foundations.

Week of January 31, 2022

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work; drill and pour foundations. Week of January 31, 2022

Stuyvesant 

  • Hollow Road: Restoration.

Stockport

  • West Ghent Road: Drill and pour foundations; structure removal and assembly.

Ghent

  • Gilligan Road: Structure removal and assembly.

  • Gregory Road: Structure removal and assembly.

  • County Road 20: Wire pull preparation.

Claverack

  • Stottville Road: Wire pull preparation.

  • Route 66: Wire pull preparation.

  • Route 23B: Drill and pour foundations.

  • Route 9H and 23: Matting and access installation.

  • Churchtown Substation (Orchard Road): Civil and below-grade work; construction of switching station.

Livingston

  • NY-82: Mowing and handcutting of vegetation.

  • Lockwood Road: Vegetation and tree removal.

  • Blue Stores Substation (County Route 19): Civil work.

  • County Route 8: Matting and access installation.

Clinton

  • Deer Hill Road: Flagging and staking.

  • Bulls Head Road: Flagging and staking.

Pleasant Valley

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Drill and pour foundations.

Week of January 24, 2022

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

  • Ridge Road: Restoration.

Stuyvesant 

  • County Road 26A: Restoration.

Stockport

  • West Ghent Road: Drill and pour foundations; structure removal.

  • Fitting Road: Drill and pour foundations; structure removal.

Claverack 

  • Route 66: Wire pull preparation.

  • Route 9H and 23B: Vegetation and tree removal; matting and access installation.

  • Churchtown Substation (Orchard Road): Civil and below-grade work; construction of switching station.

Livingston

  • Bells Pond Road: Mowing and handcutting of vegetation; matting and access installation

  • Lockwood Road: Vegetation and tree removal.

  • Blue Stores Substation (County Route 19): Mobilization.

  • County Route 8: Mobilization; matting and access installation.

Milan

  • Round Lake Road: Flagging and staking.

Clinton

  • Deer Hill Road: Flagging and staking.

Pleasant Valley

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Drill and pour foundations.

Week of January 17, 2022

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

Stuyvesant 

  • Ridge Road: Restoration.

Stockport

  • West Ghent Road: Drill and pour foundations.

  • Fitting Road: Structure removal; drill and pour foundations; structure delivery and assembly.

Claverack 

  • Stottville Road: Structure removal; structure delivery and assembly.

  • Stone Mill Road: Matting and access installation.

  • Route 9H and 23B: vegetation and tree removal.

  • Churchtown Substation (Orchard Road): Civil and below-grade work; construction of the substation; vegetation and tree removal.

  • Orchard Rd: Vegetation and tree removal.

Milan

  • Salisbury Turnpike: Flagging and staking.

  • Round Lake Road: Flagging and staking.

Pleasant Valley

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Vegetation and tree removal.

Week of January 10, 2022

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

Stuyvesant 

  • Ridge Road: Restoration.

  • Schoolhouse Road: Restoration.

  • Hollow Road: Restoration.

Stockport

  • West Ghent Road: mobilization.

  • Fitting Road: Structure removal; drill and pour foundations; structure delivery and assembly; vegetation and tree removal.

  • Begos Road: Structure removal; drill and pour foundations; structure delivery and assembly.

  • Stottville Road: Structure removal; drill and pour foundations; structure delivery and assembly.

  • NY-66: vegetation and tree removal.

Claverack 

  • Webb Road: Vegetation and tree removal; matting and access installation.

  • Stone Mill Road: Matting and access installation.

  • Churchtown Switching Station (Orchard Road): Civil and below-grade work; construction of the station.

Livingston

  • Bells Pond Road: Matting and access installation.

Milan

  • Oakland Hills Drive: Flagging and staking.

  • Salisbury Turnpike: Flagging and staking.

Pleasant Valley

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Vegetation and tree removal.

Week of January 3, 2022

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

  • Schodack Landing Road: Restoration.

Stuyvesant 

  • Ridge Road: Restoration.

  • Schoolhouse Road: Restoration.

  • Hollow Road: Restoration.

Stockport

  • West Ghent Road: Structure removal.

  • Fitting Road: Structure removal; drill and pour foundations; wirework; vegetation and tree removal.

  • Begos Road: Drill and pour foundations; wirework; vegetation and tree removal.

  • County Highway 20: Wirework; vegetation and tree removal.

  • Stottville Road: Wirework; vegetation and tree removal.

  • NY-66: Wirework; structure removal; vegetation and tree removal.

Claverack 

  • Webb Road: Vegetation and tree removal; matting and access installation.

  • Stone Mill Road: Matting and access installation.

  • Churchtown Switching Station (Orchard Road): Civil work; station construction.

Livingston

  • Bells Pond Road: Matting and access installation.

Milan

  • Battenfeld Road: Flagging and staking.

  • Oakland Hills Drive: Flagging and staking.

Pleasant Valley

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Mobilization; vegetation and tree removal.

Week of December 20, 2021

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work and restoration.

Stuyvesant 

  • Schoolhouse Road: wirework.

  • Hollow Road: wirework.

  • CR 26A: wirework.

Claverack 

  • NY-66: Drill and pour foundations.

  • Churchtown Switching Station (Orchard Road): Civil and below-grade work; vegetation removal and mowing.

Pleasant Valley

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Mobilization; access installation; tree removal.

Week of December 27, 2021

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work and restoration.

Claverack

  • Churchtown Switching Station (Orchard Road): Civil work.

Pleasant Valley

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Mobilization; access installation; vegetation removal and mowing.

Week of December 6, 2021

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work and restoration.

  • Knickerbocker Road: Access installation; restoration.

  • Schodack Landing Road: Wire work.

Stuyvesant 

  • Ridge Road: Vegetation and tree removal; restoration.

  • Schoolhouse Road: Structure removal and assembly; wire work; vegetation and tree removal.

  • Hollow Road: Structure removal and assembly; wire work; vegetation and tree removal.

  • CR 26A: Vegetation and tree removal.

  • Newton Hook Road: Vegetation and tree removal.

Stockport

  • U.S. Highway 9: Vegetation and tree removal.

  • Hudson Avenue: Vegetation and tree removal.

  • Knitt Road: Vegetation and tree removal.

Claverack 

  • NY-23B: Vegetation and tree removal; matting and access installation.

  • Webb Road: Vegetation and tree removal; matting and access installation.

  • Orchard Road: Matting and access installation; drill and pour foundations.

  • Churchtown Switching Station (Orchard Road): Civil and below-grade work; vegetation removal and mowing.

Livingston

  • Bells Pond Road: Vegetation removal and mowing.

  • NY 82: Vegetation removal and mowing.

  • Estok Road: Vegetation removal and mowing.

  • Schneider Road: Vegetation removal and mowing.

  • Church Road: Vegetation removal and mowing.

  • Lockwood Road: Vegetation removal and mowing.

  • Scudderhook Road: Vegetation removal and mowing.

  • Deer Haven Road: Vegetation removal and mowing.

  • Black Bridge Road: Vegetation removal and mowing.

Milan

  • Becker Hill Road: Flagging and staking.

  • Battenfeld Road: Flagging and staking.

Pleasant Valley

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Mobilization, access installation.

Week of November 29, 2021

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work and foundation installation.

  • Knickerbocker Road: Access installation; restoration.

Stuyvesant 

  • Ridge Road: Vegetation and tree removal.

  • Schoolhouse Road: Structure removal and assembly; wire work; vegetation and tree removal.

  • Hollow Road: Structure removal and assembly; vegetation and tree removal.

  • CR 26A: Vegetation and tree removal.

  • Newton Hook Road: Vegetation and tree removal.

Stockport

  • U.S. Highway 9: Vegetation and tree removal.

  • Hudson Avenue: Vegetation and tree removal.

  • Knitt Road: Vegetation and tree removal.

Claverack 

  • Gilligan Road: Drill and pour foundations.

  • Begos Road: Drill and pour foundations.

  • Fish and Game Road: Matting and access Installation.

  • NY-23B: Vegetation and tree removal.

  • Orchard Road: Matting and access installation.

  • Churchtown Switching Station (Orchard Road): Civil and below-grade work.

Milan

  • Turkey Hill Road: Flagging and staking.

  • Becker Hill Road: Flagging and staking.

Pleasant Valley

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Mobilization, access installation.

Week of November 22, 2021

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work and foundation installation.

  • Knickerbocker Road: Vegetation and tree removal.

  • Schodack Landing Road: Vegetation and tree removal.

Stuyvesant 

  • Ridge Road: Vegetation and tree removal.

  • Schoolhouse Road: Vegetation and tree removal.

Claverack 

  • Fish and Game Road: Matting and Access Installation.

  • Orchard Road: Matting and access installation.

  • Churchtown Switching Station (Orchard Road): Civil and below-grade work.

Livingston

  • Bells Pond Road: Vegetation removal and mowing.

  • NY 82: Vegetation removal and mowing.

  • Estok Road: Vegetation removal and mowing.

  • Schneider Road: Vegetation removal and mowing.

  • Church Road: Vegetation removal and mowing.

  • Lockwood Road: Vegetation removal and mowing.

  • Scudderhook Road: Vegetation removal and mowing.

  • Deer Haven Road: Vegetation removal and mowing.

  • Black Bridge Road: Vegetation removal and mowing.

Milan

  • Turkey Hill Road: Flagging and staking.

  • Becker Hill Road: Flagging and staking.

Pleasant Valley

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Mobilization.

Week of November 15, 2021

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work and foundation installation.

  • Knickerbocker Road: Vegetation and tree removal.

  • Schodack Landing Road: Vegetation and tree removal.

Stuyvesant 

  • Ridge Road: Vegetation and tree removal.

  • Schoolhouse Road: Vegetation and tree removal. Mobilization.

  • Hollow Road: Structure removal.

  • CR 26A: Structure removal.

Stockport 

  • US 9: Wire installation.

  • Hudson Avenue (CR 25): Wire installation.

  • Knitt Road: Wire installation.

  • W Ghent Road: Wire installation; drill and pour foundations; structure removal.

Ghent 

  • CR 20: Drill and pour foundations; matting and access installation.

Claverack 

  • Stottville Road: Drill and pour foundations.

  • Fish and Game Road: Matting and access installation.

  • Orchard Road: Drill and pour foundations; matting and access installation; vegetation removal and mowing.

  • Churchtown Switching Station (Orchard Road): Civil and below-grade work.

Livingston

  • Bells Pond Road: Vegetation removal and mowing.

  • NY 82: Vegetation removal and mowing.

  • Estok Road: Vegetation removal and mowing.

  • Schneider Road: Vegetation removal and mowing.

  • Church Road: Vegetation removal and mowing.

  • Lockwood Road: Vegetation removal and mowing.

  • Scudderhook Road: Vegetation removal and mowing.

  • Deer Haven Road: Vegetation removal and mowing.

  • Black Bridge Road: Vegetation removal and mowing.

Clermont

  • Turkey Hill Road: Flagging and staking.

Milan

  • Turkey Hill Road: Flagging and staking.

Pleasant Valley

  • Pleasant Valley Substation (Niagara Road): Civil work.

  • Van Wagner Capacitor Bank Station (Van Wagner Road): Mobilization.

Week of November 8, 2021

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

  • Knickerbocker Road: Restoration; vegetation removal.

  • Schodack Landing Road: Restoration; vegetation removal.

Stuyvesant 

  • Schoolhouse Road: Restoration; vegetation removal.

  • Hollow Road: Wire work.

  • CR 26A: Wire work.

  • CR 46: Wire work.

Stockport 

  • US 9: Wire installation preparation.

  • Hudson Avenue (CR 25): Wire installation preparation; structure removal; structure installation.

  • Knitt Road: Wire installation preparation; structure removal; structure installation; selective vegetation maintenance.

Ghent 

  • Gilligan Road: Selective vegetation maintenance.

  • Begos Road: Matting and access installation; selective vegetation maintenance.

  • CR 20: Matting and access installation; selective vegetation maintenance.

  • Stottville Road: Drill and pour foundations; selective vegetation maintenance.

Claverack 

  • Union Turnpike (Rt 66): Selective vegetation maintenance.

  • Fish and Game Road: Matting and access installation; selective vegetation maintenance.

  • NY 23B: Selective vegetation maintenance.

  • Orchard Road: Matting and access installation; mowing and handcutting of vegetation as needed.

  • Churchtown Switching Station (Orchard Road): Civil work.

Livingston

  • Bells Pond Road: Matting and access installation; mowing and handcutting of vegetation as needed.

  • Estok Road: Flagging and staking.

  • Schneider Road: Flagging and staking.

  • Church Road: Flagging and staking.

Pleasant Valley

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of November 1, 2021

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

  • Knickerbocker Road: Restoration.

  • Schodack Landing Road: Restoration.

Stuyvesant 

  • Schoolhouse Road: Restoration.

  • Hollow Road: Wire work.

  • CR 26A: Wire work.

  • CR 46: Wire work.

Stockport 

  • US 9: Wire work.

  • Hudson Avenue (CR 25): Wire work; structure removal.

  • Knitt Road: Wire installation preparation; structure removal.

Ghent 

  • Gilligan Road: Selective vegetation maintenance.

  • Begos Road: Selective vegetation maintenance.

  • CR 20: Drill and pour foundations; matting and access installation; selective vegetation maintenance.

Claverack 

  • Union Turnpike (Rt 66): Drill and pour foundations; selective vegetation maintenance.

  • Fish and Game Road: Matting and access installation; selective vegetation maintenance.

  • NY 23B: Selective vegetation maintenance.

  • Orchard Road: Matting and access installation; mowing and handcutting of vegetation as needed.

  • Churchtown Switching Station (Orchard Road): Civil work.

Livingston

  • Bells Pond Road: Matting and access installation; mowing and handcutting of vegetation as needed.

  • Estok Road: Flagging and staking.

Pleasant Valley

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of October 25, 2021

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

  • Knickerbocker Road: Restoration.

  • Schodack Landing Road: Restoration.

Stuyvesant 

  • Schoolhouse Road: Restoration.

  • Hollow Road: Structure delivery.

  • CR26A: Wire installation preparation.

  • CR 46: Wire installation preparation.

Stockport 

  • US 9: Structure assembly; wire installation preparation.

  • Hudson Avenue (C.R. 25): Structure removal, structure delivery.

  • Knitt Road: Drill and pour foundations; structure delivery.

Ghent 

  • CR 20: Drill and pour foundations; matting and access installation.

Claverack 

  • Union Turnpike (Rt 66): Drill and pour foundations.

  • Fish and Game Road: Matting and Access installation, mowing and handcutting of vegetation as needed.

  • Orchard Road: Matting and access installation; mowing and handcutting of vegetation as needed.

  • Churchtown Switching Station (Orchard Road): Civil work.

Livingston

  • Bells Pond Road: Matting and access installation; mowing and handcutting of vegetation as needed; flagging and staking.

  • Route 82: Flagging and staking.

  • Estok Road: Flagging and staking.

Pleasant Valley

  • Pleasant Valley Substation (Niagara Road): Civil work.

Week of October 18, 2021

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

  • Knickerbocker Road: Restoration.

  • Schodack Landing Road: Restoration.

Stuyvesant 

  • Schoolhouse Road: Restoration.

  • Hollow Road: Structure delivery and assembly.

  • CR26A: Structure removal; structure assembly.

Stockport 

  • US 9: Structure removal, delivery, and assembly.

  • Hudson Avenue (C.R. 25): Drill and pour foundations; structure removal; structure assembly.

  • Knitt Road: Drill and pour foundations, structure delivery; structure assembly.

Ghent 

  • CR 20: Drill and pour foundations.

Claverack 

  • Stottville Road: Drill and pour foundations.

  • Union Turnpike (Rt 66): Drill and pour foundations.

  • Fish and Game Road: Mowing and handcutting of vegetation as needed; matting and access installation.

  • NY-23B: Mowing and handcutting of vegetation as needed; matting and access installation.

  • Webb Road: Mowing and handcutting of vegetation as needed.

  • Stone Mill Road: Mowing and handcutting of vegetation as needed.

  • NY-23/ NY-9H: Mowing and handcutting of vegetation as needed.

  • Churchtown Switching Station (Orchard Road): Civil work.

Pleasant Valley

  • Pleasant Valley Substation (Niagara Road): Mobilization.

Week of October 11, 2021

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

  • Knickerbocker Road: Restoration.

  • Schodack Landing Road: Restoration.

Stuyvesant 

  • Schoolhouse Road: Restoration.

  • Hollow Road: Structure assembly.

  • CR26A: Structure assembly.

Stockport 

  • US 9: Drill and pour foundations; structure delivery; structure assembly.

  • Hudson Avenue (C.R. 25): Drill and pour foundations; structure delivery.

  • Knitt Road: Drill and pour foundations; structure delivery.

Ghent 

  • CR 20: Matting and access installation.

Claverack 

  • Union Turnpike (Rt 66): Drill and pour foundations.

  • Fish and Game Road: Mowing and handcutting of vegetation as needed; matting and access installation.

  • NY-23B: Mowing and handcutting of vegetation as needed; matting and access installation.

  • Webb Road: Mowing and handcutting of vegetation as needed.

  • Stone Mill Road: Mowing and handcutting of vegetation as needed.

  • NY-23/ NY-9H: Mowing and handcutting of vegetation as needed.

  • Churchtown Switching Station (Orchard Road): Civil work; mowing and handcutting of vegetation as needed.

Week of October 4, 2021

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

  • Knickerbocker Road: Restoration.

  • Schodack Landing Road: Restoration.

Stuyvesant 

  • Schoolhouse Road: Structure demolition.

  • Hollow Road: Structure delivery and assembly.

  • CR26A: Drill and pour foundations; structure delivery and assembly.

  • CR 46: Drill and pour foundations; structure delivery and assembly.

Stockport 

  • US 9: Structure delivery and assembly; set up for wire pulling.

  • Hudson Avenue (C.R. 25): Drill and pour foundations.

  • Knitt Road: Drill and pour foundations; structure delivery and assembly.

  • Fitting Road: Matting and access installation.

Ghent 

  • Gilligan Road: Matting and access installation.

  • Begos Road: Matting and access installation.

  • CR 20: Matting and access installation.

Claverack 

  • Union Turnpike (Rt 66): Matting and access installation.

  • Fish and Game Road: Matting and access installation.

  • NY 23B: Matting and access installation.

  • Webb Road: Mowing and handcutting of vegetation as needed.

  • Stone Mill Road: Mowing and handcutting of vegetation as needed.

  • NY 9H & 23: Mowing and handcutting of vegetation as needed.

  • Churchtown Switching Station (Orchard Road): Civil work.

Week of September 27, 2021

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

  • Knickerbocker Road: Restoration.

  • Schodack Landing Road: Restoration.

Stuyvesant 

  • Schoolhouse Road: Structure delivery and wire work.

  • Hollow Road: Drill and pour foundations; structure delivery and assembly.

  • CR26A: Drill and pour foundations; structure delivery and assembly.

  • CR 46: Drill and pour foundations; structure delivery and assembly.

Stockport 

  • US 9: Drill and pour foundations; structure delivery and assembly.

  • Hudson Avenue (C.R. 25): Drill and pour foundations.

  • Knitt Road: Drill and pour foundations.

  • W Ghent Road: Matting and access installation.

  • Fitting Road: Matting and access installation.

Ghent 

  • Gilligan Road: Matting and access installation.

  • Begos Road: Matting and access installation; mowing and handcutting of vegetation as needed.

  • CR 20: Crew mobilization; matting and access installation.

Claverack 

  • Stottville Road: Matting and access installation.

  • Union Turnpike (Rt 66): Matting and access installation.

  • Fish and Game Road: Mowing and handcutting of vegetation as needed.

  • NY 23B: Mowing and handcutting of vegetation as needed.

  • Webb Road: Mowing and handcutting of vegetation as needed.

  • Stone Mill Road: Mowing and handcutting of vegetation as needed.

  • NY 9H & 23: Mowing and handcutting of vegetation as needed.

  • Churchtown Switching Station (Orchard Road): Civil work.

Week of September 13, 2021 

Schodack 

  • Knickerbocker Switching Station (Muitzeskill Road):
    Civil work.

Stuyvesant 

  • Schoolhouse Road:
    Structure delivery and wire work.

  • Hollow Road: Drill and pour foundations; structure delivery; handcutting of vegetation as needed.

  • CR26A: Structure delivery and handcutting of vegetation as needed.

  • CR 46: Structure delivery and handcutting of vegetation as needed.

Stockport 

  • US 9: Drill and pour foundations; structure delivery; handcutting of vegetation as needed.

  • Knitt Road: Drill and pour foundations; structure delivery; mowing and handcutting of vegetation as needed.

  • W Ghent Road: Drill and pour foundations; matting and access installation; mowing and handcutting of vegetation as needed.

  • Fitting Road: Matting and access installation; mowing and handcutting of vegetation as needed.

Ghent 

  • Gilligan Road: Matting and access installation; mowing and handcutting of vegetation as needed.

  • Begos Road: Matting and access installation; mowing and handcutting of vegetation as needed.

  • CR 20: Mowing and handcutting of vegetation as needed.

Claverack 

  • Stottville Road: Matting and access installation; mowing and handcutting of vegetation as needed.

  • Union Turnpike (Rt 66): Matting and access installation; mowing and handcutting of vegetation as needed.

  • Fish and Game Road: Mowing and handcutting of vegetation as needed.

  • Churchtown Switching Station (Orchard Road): Civil work.

Week of September 6, 2021

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

  • Knickerbocker Road: Wire pulling.

  • Schodack Landing Road: Wire pulling.

Stuyvesant

  • Ridge Road: Wire pulling.

  • Schoolhouse Road: Wire pulling.

  • Hollow Road: Drill and pour foundations.

  • CR 46: Drill and pour foundations.

Stockport

  • Hudson Ave: Drill and pour foundations.

  • Knitt Road: Drill and pour foundations.

  • W Ghent Road: Matting and access installation. Mowing and handcutting of vegetation as needed.

  • Fitting Road: Matting and access installation. Mowing and handcutting of vegetation as needed.

Ghent

  • Gilligan Road: Matting and access installation. Mowing and handcutting of vegetation as needed.

  • Begos Road: Matting and access installation. Mowing and handcutting of vegetation as needed.

  • CR 20: Matting and access installation. Mowing and handcutting of vegetation as needed.

Claverack

  • Stottville Road: Matting and access installation. Mowing and handcutting of vegetation as needed.

  • Union Turnpike (Rt 66): Matting and access installation. Mowing and handcutting of vegetation as needed.

Churchtown Switching Station (Orchard Road): Civil work and drill crew mobilization.

Week of August 30, 2021

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

  • Knickerbocker Road: Wire pulling.

  • Schodack Landing Road: Wire pulling and remove old structures.

Stuyvesant

  • Ridge Road: Wire pulling.

  • Schoolhouse Road: Wire pulling. Drill and pour foundations.

  • CR 26A: Drill and pour foundations. Mowing and handcutting of vegetation as needed.

  • CR 46: Matting and access installation. Mowing and handcutting of vegetation as needed.

  • Hollow Road: Drill and pour foundations. Mowing and handcutting of vegetation as needed.

Stockport

  • US 9: Mowing, and handcutting of vegetation as needed.

  • Hudson Ave: Matting and access installation.

  • Knitt Road: Drill and pour foundations. Mowing and handcutting of vegetation as needed.

  • W Ghent Road: Matting and access installation. Mowing and handcutting of vegetation as needed.

  • Fitting Road: Matting and access installation. Mowing and handcutting of vegetation as needed.

Ghent

  • Gilligan Road: Matting and access installation. Mowing and handcutting of vegetation as needed.

Claverack

  • Stottville Road: Matting and access installation. Mowing and handcutting of vegetation as needed.

  • Union Turnpike (Rt 66): Matting and access installation. Mowing and handcutting of vegetation as needed.

  • Churchtown Switching Station (Orchard Road): Civil work.

Week of August 23, 2021

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Civil work.

  • Schodack Landing Road: Structure assembly, wire pulling, and remove old structures.

Stuyvesant

  • Ridge Road: Wire pulling.

  • Schoolhouse Road: Wire pulling. Mowing and handcutting of vegetation as needed.

  • Schoolhouse Road: Mowing and handcutting of vegetation as needed.

  • CR 26A: Mowing and handcutting of vegetation as needed.

  • CR 46: Drill and pour foundations. Matting and access installation. Mowing and handcutting of vegetation as needed.

  • Hollow Road: Drill and pour foundations. Mowing and handcutting of vegetation as needed.

Stockport

  • US 9: Drill and pour foundations. Mowing and handcutting of vegetation as needed.

  • Hudson Ave: Matting and access installation. Mowing and handcutting of vegetation as needed.

  • Knitt Road: Drill and pour foundations. Mowing and handcutting of vegetation as needed.

  • W Ghent Road: Drill and pour foundations. Mowing and handcutting of vegetation as needed.

Claverack

  • Churchtown Switching Station (Orchard Road): Civil work.

Livingston

  • Deer Haven Road, Black Bridge Road: Flagging and staking of the corridor.

Week of August 16, 2021

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Mobilization and civil work.

  • Muitzeskill Road: Remove old structures.

  • Knickerbocker Road: Structure assembly and wire work. Remove old structures.

  • Schodack Landing Road: Structure assembly and wire work. Remove old structures.

Stuyvesant

  • Ridge Road: Remove old structures.

  • Schoolhouse Road: Drill and pour foundations. Mowing and handcutting of vegetation as needed.

  • CR 26A: Mowing and handcutting of vegetation as needed.

  • CR 46: Drill and pour foundations. Matting and access installation. Mowing and handcutting of vegetation as needed.

  • Hollow Road: Matting and access installation. Mowing and handcutting of vegetation as needed.

Stockport

  • US 9: Mowing and handcutting of vegetation as needed.

  • Hudson Avenue: Matting and access installation. Mowing and handcutting of vegetation as needed.

  • Knitt Road: Mowing and handcutting of vegetation as needed.

  • W Ghent Road: Mowing and handcutting of vegetation as needed.

Claverack

  • Churchtown Switching Station (Orchard Road): Civil work.

Livingston

  • Lockwood Road, Scudderhook Road: Flagging and staking of the corridor.

Week of August 9, 2021

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Mobilization and vegetation removal.

  • Muitzeskill Road: Material delivery and structure spotting and assembly.

  • Knickerbocker Road: Material delivery and structure spotting and assembly.

  • Schodack Landing Road: Material delivery and structure spotting and assembly.

Stuyvesant

  • Ridge Road: Material delivery and structure spotting and assembly.

  • Schoolhouse Road: Drill and pour foundations.

  • CR 26A: Drill and pour foundations.

  • CR 46: Matting and access installation. Mowing and handcutting of vegetation as needed.

  • Hollow Road: Matting and access installation. Mowing and handcutting of vegetation as needed.

Stockport

  • US 9: Matting and access installation. Mowing and handcutting of vegetation as needed.

  • Knitt Road: Matting and access installation. Mowing and handcutting of vegetation as needed.

  • W Ghent Road: Matting and access installation. Mowing and handcutting of vegetation as needed.

  • CR 25: Mowing and handcutting of vegetation as needed.

Claverack

  • Churchtown Switching Station (Orchard Road): Civil work.

Livingston

  • Lockwood Road, Scudderhook Road, Deer Haven Road, Black Bridge Road, County Hwy 8, White Oak Road: Flagging and staking of the corridor.


Week of August 2, 2021

Schodack

  • Knickerbocker Switching Station (Muitzeskill Road): Mobilization, access work, and vegetation removal.

  • Muitzesill Road, Knickerbocker Road: Drill and pour foundations.

  • Schodack Landing Road: Drill and pour foundations. Structure assembly. Material delivery and spotting.

Stuyvesant

  • Ridge Road: Structure assembly. Material delivery and spotting.

  • Schoolhouse Road: Material delivery and spotting.

  • Hollow Road, CR 26A, Allendale Road, CR 46: Matting and access installation. Mowing and handcutting of vegetation as needed.

Stockport

  • Knitt Road: Matting and access installation. Mowing and handcutting of vegetation as needed.

  • US 9, CR 25, W Ghent Road: Mowing and handcutting of vegetation as needed.

Claverack

  • Churchtown Switching Station (Orchard Road): Civil work.

Livingston

  • Church Road, Lockwood Road, Scudderhool Road, Deer Haven Road, Black Bridge Road: Flagging and staking of the corridor.


Week of July 26, 2021

Schodack

  • Structure delivery to the corridor and erection.

  • Muitzeskill Road: Environmental controls and access installation, as well as civil work at Knickerbocker Switching Station site.

  • Schodack Landing Road: Drill and pour foundations.

Stuyvesant

  • Structure delivery to the corridor and erection.

  • Ridge Road: Drill and pour foundations.

  • Hollow Road, CR 26A, Allendale Road, CR 46: Matting and access installation. Mowing and handcutting of vegetation as needed.

Stockport

  • Knitt Road: Matting and access installation. Mowing and handcutting of vegetation as needed.

  • US 9, CR 25, W Ghent Road: Mowing and handcutting of vegetation as needed.

Ghent

  • Begos Road, Cty Hwy 20: Flagging and staking of the corridor.

Claverack

  • Stottville Road, Union Tpk (Rt. 66), Fish and Game Road, State Hwy 23B, Webb Road, Stone Mill Road, Route 9H and 23, School House Road: Flagging and staking of the corridor.

  • Orchard Road: Civil work at Churchtown Switching Station.


Week of July 19, 2021

Schodack

  • Muitzeskill Road: Mobilization to the Knickerbocker Switching Station area begins. Matting and access installation.

  • Schodack Landing Road: Drill and pour foundations. Structure delivery to the corridor.

Stuyvesant

  • Ridge Road, Schoolhouse Road: Drill and pour foundations. Deliver, set and erect structures.

  • Hollow Road, CR 26A, Allendale Road, CR 46: Matting and access installation. Mowing and handcutting of vegetation as needed.

Stockport

  • Knitt Road: Matting and access installation. Mowing and handcutting of vegetation as needed.

  • US 9, CR 25, W Ghent Road: Mowing and handcutting of vegetation as needed.

Ghent

  • Begos Road, Cty Hwy 20: Flagging and staking of the corridor.

Claverack

  • Stottville Road, Union Tpk (Rt. 66), Fish and Game Road, State Hwy 23B, Webb Road, Stone Mill Road, Route 9H and 23, School House Road: Flagging and staking of the corridor.

  • Orchard Road: Demolition and civil work at Churchtown Switching Station.


Week of July 12, 2021

Schodack

  • Structure delivery to the corridor.

  • Knickerbocker Road: Matting installation.

  • Knickerbocker Road, Schodack Landing Road: Drill and pour foundations.

Stuyvesant

  • Structure delivery to the corridor.

  • Schoolhouse Road, Hollow Road, CR 26A: Matting and access installation.

  • Ridge Road: Drill and pour foundations.

  • Ridge Road, Schoolhouse Road: Set and erect structures.

  • Schoolhouse Road, Hollow Road, CR 26A, Allendale Road, CR 46: Mowing and handcutting of vegetation as needed.

Stockport

  • US 9, CR 25, Knitt Road, W Ghent Road: Mowing and handcutting of vegetation as needed.

Ghent

  • Begos Road, Cty Hwy 20: Flagging and staking of the corridor.

Claverack

  • Stottville Road, Union Tpk (Rt. 66), Fish and Game Road, State Hwy 23B, Webb Road, Stone Mill Road, Route 9H and 23, School House Road: Flagging and staking of the corridor.

  • Orchard Road: Demolition and civil work at Churchtown Switching Station.


Week of July 5, 2021

Schodack

  • Structure delivery to the corridor.

  • Knickerbocker Road, Muitzeskill Road: Drill and pour foundations.

Stuyvesant

  • Structure delivery to the corridor.

  • Schoolhouse Road, Hollow Road, CR 26A: Matting and access installation.

  • Ridge Road: Drill and pour foundations.

  • Schoolhouse Road, Hollow Road, CR 26A, Allendale Road, CR 46: Mowing and handcutting of vegetation as needed.

Stockport

  • US 9, CR 25, Knitt Road, W Ghent Road: Mowing and handcutting of vegetation as needed.

Ghent

  • Begos Road, Cty Hwy 20: Flagging and staking of the corridor.

Claverack

  • Stottville Road, Union Tpk (Rt. 66), Fish and Game Road, State Hwy 23B, Webb Road, Stone Mill Road: Flagging and staking of the corridor.

  • Orchard Road: Demolition and civil work at Churchtown Switching Station.


Week of June 28, 2021

Schodack

  • Knickerbocker Road, Schodack Landing Road: Drill and pour foundations.

Stuyvesant

  • Schoolhouse Road, Hollow Road, CR26A: Matting and access installation.

  • Ridge Road, Schoolhouse Road: Drill and pour foundations.

  • Schoolhouse Road, Hollow Road, CR 26A, Allendale Road, CR46: Mowing and handcutting of vegetation as needed.

Stockport

  • US 9, CR 25, Knitt Road, W Ghent Road: Mowing and handcutting of vegetation as needed.

  • CR 25: Foundation testing.

  • W Ghent Road: Flagging and staking of the corridor.

Ghent

  • Begos Road, Cty Hwy 20: Flagging and staking of the corridor.

Claverack

  • Stottville Road, Union Tpk (Rt. 66), Fish and Game Road, State Hwy 23B, Webb Road, Stone Mill Road: Flagging and staking of the corridor.

  • Orchard Road: Mobilization and demolition work at Churchtown Switching Station.


Week of June 21, 2021

Schodack

  • Muitzeskill Road, Knickerbocker Road, Schodack Landing Road: Drill and pour foundations.

  • Schodack Landing Road: Matting and access installation, including mowing.

Stuyvesant

  • Schoolhouse Road, Hollow Road, CR26A: Matting and access installation, including mowing.

  • Ridge Road, Schoolhouse Road: Drill and pour foundations.

  • Schoolhouse Road, Hollow Road, CR 26A, Allendale Road, CR46: Mowing and handcutting of vegetation as needed.

Stockport

  • US 9, CR 25, Knitt Road, W Ghent Road: Mowing and handcutting of vegetation as needed.

  • CR 25: Foundation installation and testing.

Ghent

  • Begos Road, Cty Hwy 20: Flagging and staking of the corridor. Mowing and handcutting of vegetation as needed.

Claverack

  • Stottville Road, Union Tpk (Rt. 66), Fish and Game Road, State Hwy 23B, Webb Road, Stone Mill Road: Flagging and staking of the corridor. Mowing and handcutting of vegetation as needed.

  • Orchard Road: Work at Churchtown Switching Station.


Week of June 14, 2021

Schodack

  • Muitzeskill Road, Knickerbocker Road: Drill and pour foundations.

  • Schodack Landing Road: Matting and access installation, including mowing.

Stuyvesant

  • Ridge Road, Schoolhouse Road: Matting and access installation, including mowing.

  • Schoolhouse Road: Drill and pour foundations.

  • Schoolhouse Road, Hollow Road, CR 26A, Allendale Road, CR46: Mowing and handcutting of vegetation as needed.

Stockport

  • US 9, CR 25, Knitt Road, W Ghent Road: Mowing and handcutting of vegetation as needed.

  • CR 25: Foundation installation and testing.

Ghent

  • Begos Road, Cty Hwy 20: Flagging and staking of the corridor. Mowing and handcutting of vegetation as needed.

Claverack

  • Stottville Road, Union Tpk (Rt. 66), Fish and Game Road, State Hwy 23B, Webb Road, Stone Mill Road: Flagging and staking of the corridor. Mowing and handcutting of vegetation as needed.

  • Baker Road Laydown Yard: Utilities installed.


Week of June 7, 2021

Schodack

  • Muitzeskill Road, Knickerbocker Road: Drill and pour foundations.

  • Schodack Landing Road: Matting and access installation, including mowing.

Stuyvesant

  • Ridge Road, Schoolhouse Road: Matting and access installation, including mowing.

  • Schoolhouse Road: Drill and pour foundations.

  • Schoolhouse Road, Hollow Road, CR 26A, Allendale Road, CR46: Flagging and staking of the corridor. Mowing and handcutting of vegetation as needed.

Stockport

  • US 9, CR 25, Knitt Road, W Ghent Road: Flagging and staking of the corridor. Mowing and handcutting of vegetation as needed.

  • CR 25: Foundation installation and testing.

Ghent

  • Begos Road, Cty Hwy 20: Flagging and staking of the corridor. Mowing and handcutting of vegetation as needed.

  • Falls Industrial Park Road: Fencing at Falls Industrial Park Road Laydown Yard.

Claverack

  • Stottville Road, Union Tpk (Rt. 66), Fish and Game Road, State Hwy 23B, Webb Road, Stone Mill Road: Flagging and staking of the corridor. Mowing and handcutting of vegetation as needed.

  • Baker Road: Fencing at Baker Road Laydown Yard.


Week of June 1, 2021

Schodack

  • Knickerbocker Road, Schodack Landing Road: Matting and access installation, including mowing.

Stuyvesant

  • Ridge Road, Schoolhouse Road: Matting and access installation, including mowing.

  • Ridge Road, Schoolhouse Road, Hollow Road, CR 26A, Allendale Road, CR46: Mowing and handcutting of vegetation as needed.

Stockport

  • US 9, CR 25, Knitt Road, W Ghent Road, Fitting Road: Mowing and handcutting of vegetation as needed.

Ghent

  • Begos Road, Cty Hwy 20: Flagging and staking of the corridor. Mowing and handcutting of vegetation as needed.

Claverack

  • Stottville Road, Union Tpk (Rt. 66), Fish and Game Road, State Hwy 23B, Webb Road: Flagging and staking of the corridor. Mowing and handcutting of vegetation as needed.


Week of May 24, 2021

Schodack

  • Muitzeskill Road, Knickerbocker Road, Schodack Landing Road: Matting and access installation, including mowing.

Stuyvesant

  • Ridge Road, Schoolhouse Road, Hollow Road, CR 26A, Allendale Road, CR46: Flagging and staking of the corridor. Mowing and handcutting of vegetation as needed.

  • Ridge Road, Schoolhouse Road: Matting and access installation, including mowing.

Stockport

  • US 9, CR 25, Knitt Road, W Ghent Road: Flagging and staking of the corridor. Mowing and handcutting of vegetation as needed.

Ghent

  • Falls Industrial Park Road: Continued buildout of Falls Industrial Park Road Laydown Yard.

Claverack

  • Baker Road: Continued buildout of Baker Road Laydown Yard.


Week of May 17, 2021

Schodack

  • Muitzeskill Road, Knickerbocker Road, Schodack Landing Road: Matting and access installation, including mowing.

Stuyvesant

  • Ridge Road, Schoolhouse Road, Hollow Road, CR 26A, Allendale Road, CR46: Flagging and staking of the corridor. Mowing and handcutting of vegetation as needed.

  • Ridge Road, Schoolhouse Road: Matting and access installation, including mowing.

Stockport

  • US 9, CR 25, Knitt Road, W Ghent Road: Flagging and staking of the corridor. Mowing and handcutting of vegetation as needed.

Ghent

  • Falls Industrial Park Road: Continued buildout of Falls Industrial Park Road Laydown Yard.

Claverack

  • Baker Road: Continued buildout of Baker Road Laydown Yard.

  • Orchard Road: Churchtown Shoofly structure setting and wire pulling.


Week of May 10, 2021

Schodack

  • Muitzeskill Road, Knickerbocker Road, Schodack Landing Road: Matting and access installation, including mowing.

Stuyvesant

  • Ridge Road, Schoolhouse Road, Hollow Road, CR 26A, Allendale Road, CR46: Flagging and staking of the corridor.

  • Ridge Road, Schoolhouse Road: Matting and access installation, including mowing.

Stockport

  • US 9, CR 25, Knitt Road, W Ghent Road: Flagging and staking of the corridor.

Claverack

  • Orchard Road: Churchtown Shoofly structure work.


Week of May 3, 2021

Schodack

  • Muitzeskill Road, Knickerbocker Road, Schodack Landing Road: Matting and access installation, including mowing.

Stuyvesant

  • Ridge Road, Schoolhouse Road, Hollow Road, CR 26A, Allendale Road, CR46: Flagging and staking of the corridor.

  • Ridge Road, Schoolhouse Road: Matting and access installation, including mowing.

Stockport

  • US 9, CR 25, Knitt Road, W Ghent Road: Flagging and staking of the corridor.

Ghent

  • Falls Industrial Park Road: Continued buildout of Falls Park Industrial Road Laydown Yard.

Claverack

  • Baker Road: Continued buildout of Baker Road Laydown Yard.


Week of April 26, 2021

Schodack

  • Muitzeskill Road, Knickerbocker Road, Schodack Landing Road: Matting and access installation.

Stuyvesant

  • Ridge Road, Schoolhouse Road, Hollow Road, CR 26A, Allendale Road, CR46: Flagging and staking of the corridor.

  • Ridge Road, Schoolhouse Road: Matting and access installation.

Stockport

  • US 9, CR 25, Knitt Road, W Ghent Road: Flagging and staking of the corridor.

Ghent

  • Falls Industrial Park Road: Continued buildout of Falls Park Industrial Road Laydown Yard.

Claverack

  • Baker Road: Continued buildout of Baker Road Laydown Yard.

  • Orchard Road: Drill and install Churchtown Shoofly foundations. Pole spotting for Churchtown Shoofly.


Week of April 19, 2021

Schodack

  • Muitzeskill Road, Knickerbocker Road, Schodack Landing Road: Flagging and staking of the project corridor.

Stuyvesant

  • Ridge Road, Schoolhouse Road: Flagging and staking of the project corridor.

Claverack

  • Baker Road: Continued buildout of Baker Road Laydown Yard.

  • Orchard Road: Drill and install Churchtown Shoofly foundations.

Ghent

  • Falls Industrial Park Rd: Continued buildout of Falls Industrial Park Road Laydown Yard.


Week of April 12, 2021

Schodack

  • Muitzeskill Road, Knickerbocker Road, Schodack Landing Road: Flagging and staking of the project corridor.

Stuyvesant

  • Ridge Road, Schoolhouse Road: Flagging and staking of the project corridor.

Claverack

  • Baker Road: Grading, earthwork, and fence installation at Baker Road Laydown Yard.

  • Orchard Road: Mobilization of crews and materials for Churchtown Shoofly foundations.

Ghent

  • Falls Industrial Park Rd: Fencing installed at the Falls Industrial Park Road Laydown Yard.


Week of April 5, 2021

Claverack

  • Baker Road: Grading and earthwork at the Baker Road Laydown Yard.

  • Orchard Road: Matting installation for Churchtown Shoofly.

Ghent

  • Falls Industrial Park Rd: Grading and earthwork at the Falls Industrial Park Road Laydown Yard.


Week of March 29, 2021

Claverack

  • Baker Road: Grading and earthwork at the Baker Road Laydown Yard.

  • Orchard Road: Matting installation for Churchtown Shoofly.

Ghent

  • Falls Industrial Park Rd: Environmental controls installation at the Falls Industrial Park Road Laydown Yard.


Week of March 22, 2021

Claverack

  • Baker Road: Grading and earthwork at the Baker Road Laydown Yard.

  • Orchard Road: Mobilization and vegetation removal at the Churchtown Shoofly area.

Ghent

  • Falls Industrial Park Rd: Mobilization and vegetation removal at the Falls Industrial Park Road Laydown Yard.


Week of March 15, 2021

Claverack

  • Mobilization to the project site continues

  • Baker Road: Environmental controls continue to be installed at the laydown yard. Vegetation removal and site grading will begin at the yard this week.

  • Orchard Road: Installation of environmental controls and vegetation removal begins for Churchtown rebuild.


Week of March 8, 2021

Claverack

  • Mobilization to the project site continues

  • Baker Road: Environmental controls installed at the laydown yard


Week of March 1, 2021

Claverack

  • Crews mobilizing for Churchtown substation rebuild

  • Orchard Road: Vegetation removal for Churchtown rebuild