These photos provide a visual simulation of the work we plan to perform on an existing utility corridor and utility-owned property in Pleasant Valley. We will:

• Remove 80-year-old lattice structures (82 total, in sets of two) as shown in the photo at left.
• Retire three 115 kV transmission lines.
• Install 44 new double circuit monopole structures, with an average height increase of 10 feet, carrying one existing 115 kV line and a new 345 kV line, as shown in the photo at right.

These lines currently cross, and will continue to cross: Ward Road, Netherwood Road, Salt Point Turnpike and West Road.

Upgrades will be done at the existing Pleasant Valley Substation. Additionally, capacity banks will be installed in Pleasant Valley. Capacitor banks are a state of the art technology that allow for increased and more efficient power flow

If you have questions about our work in Pleasant Valley, please contact us at info@ny-es.com or toll-free at 1-855-433-3611.

Information may also be available at the Town of Pleasant Valley website.

Screen Shot 2019-08-08 at 10.43.39 AM.png

See the Pleasant Valley line in Google Maps

Click the map below to search for your property in relation to the transmission line. Note: Clicking the map will take you off the NY-ES website and into Google Maps.

Directions for use:

  1. After clicking the map, navigate to the upper right corner of the window and click the icon “View Larger Map.”

  2. Look for the search icon on the upper left side of this new window. Click the search icon.

  3. Type your address and hit return. An icon will denote the approximate location of your property.

  4. Zoom in or out as needed.